Park Place-CS 910617MEMO~
Mr. Mike Allen,
early release
project.
representing Allen Property Corporation, has requested
for building construction on a portion of the above listed
Please see attachment for lot and
The subdivision development is
standards.
block description of area requested.
in compliance with the City of Coppell
Early release of building construction is recommended with the
understanding that no Certificate of Occupancy will be issued until the
entire project development has met final acceptance requirements.
If you have any questions, please let me know.
Thank you.
LD/lsg
xc:
Mike Allen, Allen Properties
Tom Wise, Wiseco Development
Bill Anderson, Dowdey Engineers
Shohre Daneshmand, P.E., Acting City Engineer
Ben dela Cruz, Engineering Technician
Rey Gonzales, Street Superintendent
Howard Pafford, Water Superintendent
JUN 25 1991
PU~; !~-'~ WORKS
Troy Glidewell, Fire Marshal
Gary L. Sieb, Director of Planning & Community Services
Taryon Bowman, P&Z Coordinator
PPLACE.REL
ALLEN PROPERTY CORPORATION
12770 COIT ROAD · SUITE 1215 · DALLAS, TEXAS 75251
Telephone 214-233-5771 / Fax 214-233-5881
June 7, 1991
Mr. Larry Davis
Engineering Department
City of Coppell
City Hall
255 East Parkway Boulevard
Coppell, Texas 75019
Re: Park Place Addition
Dear Larry:
I am writing this letter to let you know that we plan on requesting in the near future an
approval of a portion of the referenced subdivision for early release of building permits. The
four builders who will be building in this subdivision are Carmen Homes, Street Homes, Mike
Clements Homes, and Brian Dalton Homes, all of which have existing contracts 1o start homes as
soon as lots are available.
The area of the subdivision for which we will first request the early release is outlined on the
enclosed copy of the plat, and encompasses Lots 11-17 in Block A, Lots 6-12 and 13-20 in
Block C, and Lots 11 and 12 in Block D. We believe this group of lots can be brought to your
requirements in a very short period of time and encompass a significant portion of the new
homes to be first built. We will be in touch with you by telephone sometime around the 111h or
12th of June, weather permitting, in order lo request a walk through of this particular portion
of Park Place. If you have any questions, please call.
Yours very truly,
Al ! FN PROPERTY CORPORATION
Michael R. Allen, President
MRA/kcb
Enclosure
cc: Mr. Tom Wise
60'
ABQ
DEVELOPMENT
ZONED TC
PECAN HOLLOW
60'
MARY BETH SOKORA SHIELDS GEORGE
ZONED SF I~.
CHADICK 14 I
t5
sANDY
7