ST9301-CS 940208 T
DALLAS COUNTY
PUBLIC WORKS
February 8, 1994
Mr. Ken Griffin, P.E.
City Engineer
City of Coppell
P.O. Box 478
255 Parkway
Coppell, Texas 75019
Re:
Sandy Lake Road Project 91-830
(MacArthur Boulevard to Coppell Fast City Limit)
Funding Summary
Dear Mr. Griffin:
The following chart is to provide you with some early preliminary estimated cost figures on this
project as you requested. The figures are ones which I prepared and are not figures from the
Consultant.
Sandy Lake Project 91-830
(Length $,065 Feet)
DESCRIFrION AMOUNT
Engineering Services $130,000.00
Construction $2,550,000.00
(Includ~es 3 % contingency)
Right-of-Way (20 parcels by Coppell) -0-
Administration (5 %) $125,000.00
Materials Testing (1%) 25,000.00
TOTAL PROJECT COST $2,830,000.00
City Reimburseables (Traffic items, ete 5%) -$125,000.00
1991 Bond Authorization $3,600,000.00
Project Shortfall -0- ·
City of Coppell Funding Required $125,000.00
411 Elm Street
Dallas, Texas 75202
653-7151
Mr. Ken Griffin, P.E.
February 8, 1994
Page Two
The City of Coppell funding responsibility includes:
The cost of the acquisition of all fight-of-way parcels needed for this project.
This includes not only the roadway right-of-way needed, but all drainage
easements and temporary construction easements as well.
The cost of all traffic related items such as striping, buttons, pavement advisory
markings, signal foundations and traffic conduit.
The cost of any irrigation and street lighting conduit, bike lane pavement, new
(not replacement) sidewalk construction.
The cost of water and sanitary sewer relocation, adjustment or betterment work
to be included in our construction plans.
5. The cost of any project funding shortfall which occurs.
If you have any questions, please advise. Our current estimated construction award date is
November 1995.
Sincerely,
BF_J:vjm