Park West CC(12)-CS010905COPP-P_.LL
September 5, 2001
Rick Stull
McFadden & Miller Inc.
11350 Luna Road
Dallas, Texas 75229
Parkwest Commerce Center, Phase m, Lot IR, Block 7 (Buildings 4 & 5)
Final Acceptance
Dear Rick:
A final inspection of paving and utilities for the referenced project has been confirmed by
representatives of the City of Coppell.
The two-year maintenance bonds and as-built drawings have been received from the contractor.
Maturity on the bonds will be two years from the date of this letter. Maturity on the Erosion
Control Bond will also be two years from the date of this letter.
Sincerel'
CC:
Ken Griffin, Director of Engineering & Public Works
Rhonda Brothers, Engineering
~~i ~~ 0f ~hC Works
Greg Jones, Chief Building Official
Travis Crump, Fire Marshal