ST9301-CS 921202DALLAS COUNTY COMMISSIONER PRECINCT NO. 1 JIM JACKSON December 2, 1992 Mr. Alan Ratliff P.O. Box 478 Coppell, TX 75019 Dear Alan, Enclosed is a current status report on the road projects from the 199]. Dallas County Bond program. One correction to Bud's report - in the last paragraph we should say that these locations have received current year plan designation in the Regional Transit Plan for funding under the Congestion Mitigation Air Quality category of ISTEA. In addition, the Turnpike Authority Board has recently approved the construction of a toll tunnel under Addison Airport that will connect Keller Springs Road. This project should continue regardless of the outcome of negotiations between the County and the Turnpike Authority concerning transferring Dallas County tollway operations to the County. In the recent election, I was re-elected for a new four year term beginning January 1, 1993. I look forward to working with you during the coming years. Thank you for your continued confidence and support. Please tell me whenever you believe that I, or Dallas County government, can or should do better. Together we can make this an even better place. I hope the Holiday Season is a joyful one for you and yours. Sincerely, SERVICE CENTER: · 2311 JOE FIELD RD. * DALLAS, TEXAS 75229 · (214) 247-1735 COUNTY ADMINISTRATION BUILDING: · 411 ELM STREET · DALLAS, TEXAS 75202 · (214) 653-7361 DALLAS COUNTY PUBLIC WORKS November 18, 1992 MEMORANDUM TO: FROM: SUBJECT: Commissioner Jim Jackson Allen Bud Beene, P.E., Director of Public Works~ Status of 1991 Bond Program Projects The following status update of 1991 Bond Program projects is provided information. Th0rouahfare Proiects Abrams Road 91-827 (Spring Valley to City Limits) · design underway by County Staff Audelia Road 91-828 (Centennial to Buckingham) · co-funded project with City of Richardson - construction complete Buckingham Road 91-831 (Audelia to Centennial) · design contract awarded to Brockette Davis Drake, Inc. - 32 weeks for completion exclusive of review time  Sandy Lake Road 91-830 (MacArthur to Coppell City Limits) · design contract awarded to Sverdrup Corporation - 30 weeks for completion exclusive of review time Sandy Lake Road 91-839 {Coppell City Limits to Carrollton City Limits) · design contract awarded to Charles Gojer, Inc. - 43 weeks for completion exclusive of review time Sandy Lake Road 91-839 (Carrollton City Limits to Old Denton Drive) · design contract awarded to Kimley-Horn, Inc. - 46 weeks for completion exclusive of review time for your use and 411 Elm Street Dallas, Texas 75202 653-7151 Commissioner Jim Jackson November 18, 1992 Page Two In addition to these projects, proposals for design services have been received and are being evaluated for the following projects. City of Dallas Denton Drive and Denton Drive/Harry Hines Boulevard Connection, Project 91-832 (Lombardy Lane to Farmers Branch City Limits) Length of Project = 3.46 miles Scope - Phase ~, Lombardy Lane to Farmers Branch City Limits Utilize City alignment and ROW surveys and perform all design (supplemental design and ROW surveys may be necessary) Design 4-lane undivided thoroughfare with left and right turn lanes shown on alignment Prepare supplemental right-of-way documents Prepare complete construction plans and documents Scope - Phase II, Denton Drive/Harry Hines Boulevard Connection Perform traffic analysis and preliminary alignment layout study with photography for a direct two-way connection South of Forest Lane (scale 1" Upon approval of connection by City perform design and ROW surveys Design roadway connection Prepare rights-of-way documents Prepare complete construction plans and documents aerial = 50') City of Farmers Branch Denton Drive/Rossford Drive and Denton Drive/Harry Hines Boulevard Connection, Project 91-833 (Farmers Branch South City Limits to Farmers Branch North City Limits) Length of Project = 1.630 miles Scope - Phase I, South City Limits to North City Limits Perform design and ROW surveys Design 4-lane undivided thoroughfare with left turn lanes at Valley View Lane and Valwood Parkway Provide Geotechnical Subsurface Investigation for bridge structures (City has hydraulic study for streams) Provide right-of-way documents Prepare complete construction plans and documents Scope - Phase II, Denton Drive/Harry Hines Boulevard Connection Perform preliminary alignment study with aerial photograph for a direct two-way Commissioner Jim Jackson November 18, 1992 Page Three connection north of IH635/LBJ Freeway (scale 1" = 50') City has traffic analysis study Upon approval of connection by City perform design and ROW surveys Design roadway connection Prepare rights-of-way documents Prepare construction plans and documents City of Irving O'Connor Road, Project 91-836 (Spur 348/Northwest Highway to proposed SH 161Nalley View Lane) Length of Project = 2.64 miles Scope Perform all design and ROW surveys Design north bound 3-lanes of 6-lane divided thoroughfare (southbound lanes existing) Design to include double left turn lanes and right turn lanes at Spur 348, Walnut Hill Lane, Royal Lane, Buffalo Boulevard with provisions for right turns at two additional locations Provide Geotechnical Subsurface Investigation for bridge structures (Hydraulic studies will not be required) Provide rights-of-way documents Prepare complete construction plans and documents City of Dallas Regal Row, Project 91-837 (Railtran RR ROW/formerly CRI & PPR to IH35E/Stemmons Freeway) Length of Project = 2.10 miles Scope Perform all design and ROW surveys Design outside 4-lanes of ultimate 6-lane divided thoroughfare (reconstruction of existing pavement) Design to include bike lanes and some roadway realignment Prepare rights-of-way documents Prepare complete construction plans and documents Prioritization for construction funding for the thoroughfare projects will be based on projects where right-of-way acquisition and utility adjustments are completed. Every effort will be made to coordinate these efforts with the respective cities. Commissioner Jim Jackson November 18, 1992 Page Four On November 10, 1992, the Commissioners Court approved a reallocation of bond funds for certain projects. The reallocation revised when funds would be expended for these projects. No adjustments were made on how much will be expended for the projects. The impacted projects were intersection improvements at the following locations: 91-593 91-594 91-595 91-719 91-724 Trinity Mills at Old Denton Road Inwood Road at Park Lane Coit Road at Belt Line Road Josey I_ane at Belt Line Road Dallas North Tollway at Spring Valley Road These locations have also received funding from the Intermodal Surface Transportation Efficiency Act (ISTEA) under the Congestion Mitigation Air Quality (CMAQ) category. This program requires a 20 percent match from local government. Adequate funding remains in the impacted projects to meet this requirement. ABB:rem file:AB~:91 ~tat.bmo