WA9801-CS 990910H & W UTILITY CONTRACTORS
September 10, 1999
Mr. Gary C. Hendricks, P. E.
Shimek, Jacobs & Finklea, L.L.P.
8333 Douglas Avenue, #820
Dallas, Texas 75225-5816
City of Coppell
State Highway 121 Water Line
Dear Gary:
Due to the shut down of this project we request a change order for remobilization when
the conflict is settled. The cost to remobilize will be $4,200.00. We also request a change
order to the cover the cost of barricades and traffic control while the project is on hold.
The daily cost of this item is $55.00 per calendar day.
Thanks for your consideration in this matter.
Sincerely,
Michael S. Haynes
President