Robertson Pools-CS 981104The City With A Beautiful Future
I~O. BOX 478
COPPELL, TEXAS 75019
RO. Box 478
Coppell, Texas 75019
972462-0022
Ron Robert.son
Robertson Commercial Pools
$69 S. Coppell Road
Coppell, Tx 75019
Robertson Commercial-'Poo]s Addition, Lot 1, Block A
Development Fee Assessment
November 4, 1998
Dear Mr. Robertson:
Enclosed is a copy of the City of Coppell Developmem Fee Assessment table, along with a copy
of the Development Fee calculations for the referenced development.
Please make payment to the City of Coppell in the anaount of $1,514.95 and forward to the
Finance Depaxixaent along with a copy of the Fee Assessment table.
Providing a copy of your paid receipt to the Engineering Department will help us to verify the
payment of required fees and insure a successful beginning of this project. We look forward
to working with you on this project. If you have any questions, please contact me.
Michael A. Martin, P.E.
Assistant City Engineer
CC;
Sennifer Armstrong, Finance Director
Doug Stevens, Engineering Technician
Greg Jones, Chief Building Official
Gary Sims, Director of Leisure Services
DEVELOPMENT FEE WORKSHEET
PROJECT: Robertson Cotntnercial Pools Addition, Lot 1, Block A
DATE: 11/4/98
Water Impact Fee:
Domestic Meter(s):
Irrigation Metar(s):
Fireline Meter(s):
Total #: 0 ESU's @ $450.00 ea.
(100% due prior to Council approval of the final plat)
Water Tap Inspection Fee:
Total 0: 0 C~nnections ~ $50.00 ea.
(Single family due prior to issuance of building permit)
(All other developments due prior to issuance of meter)
Domestic Water Meter Fee:
Total #: 0 Domestic Meter(s) @ $0.00
(Single family due prior to issuance of building permit)
(Ail other developments due prior to issuance of meter)
lrHgation/Fireline Water Meter Fee:
Total 0: 0 Irrigation Meter(s) @
Total #: 0 . Additional Irrigation Metar(s) ~
Total #: 0 Fireline Metar(s) @
(100% due prior to issuance of water meters)
Domestic Water Meter Deposit Fee:
Total #: 0 Meter(s) @ $35.00 ea.
(100% due prior to issuance of watar meters)
Irrigation/Fire Meter Deposit Fee:
Total #: 0 Meter(s) @ $30.00 ea.
(100% due prior to issuance of water meters)
Wastewater Impact Fee:
Total Domestic Meters ESU's:
0
@ $450.00 ea.
Wastewater Tap Inspection Fee:
Total #: 0 Connections @ $50.00 ea.
(100% due prior to issuance of building permit)
Utilit~ Final Inspeetion Fee (AH developments):
Total 0: 0 Lots ~ $50.00 ea.
(100% due prior to issuance of building permit)
ESU's
ESU's
ESU's
ESU's
$0.00
$o.oo
$o.oo
$o.oo
$0.00
$0.00
$0.00
$0.00
$0.00
Page 1
DEVELOPMENT FEE WORKSHEET
Park Fee (For Residential Developments Only):
* Preliminary plat approved prior to June 23, 1992:
NIA
NIA
Single-family @ $150.00 / Lot
Multi-family ~ $75.00 / Unit
(50% paid prior to Council approval of final plat)
(50% paid at issuance of building permit)
* Preliminary plat approved after June 23, 1992:
N/A
N/A
Single-family @ $350.00 / Lot
Multi-family @ $350.00 / Unit
(50% paid prior to Council approval of final plat)
(50% paid at issuance of building permit)
* Preliminary plat approved after October 26, 1993:
N/A
N/A
Single-family ~ $1285.00 / Lot
Multi-family @ $1285.00 / Unit
(100% paid prior to Council approval of final plat)
Roadway Impact Fee:
(See attached fee calculations)
Street Lighting Fees:
Assessed for lighting in the City's right-of-way.
This fee cannot be assessed until after T.U. Electric submits
the lighting plan for the proposed development.
Once the plans are submitted, $292.60 per light will be assessed.
(100% due prior to final acceptance of development)
N/A
N/A
N/A
N/A
N/A
$1,514.95
N/A
Street Sign Fees:
Assessed for signage in the City's right-of-way.
(See attached fee calculations if applicable)
N/A
Construction Inspection Fees:
A copy of the development contract must be submitted for assessmenL
The contracts should indicate the cost to construct the improvements
that are inspected by the Engineering Department.
(2% of development cost required for private improvements)
(4% of development cost required for public improvements)
NIA
Page 2
DEVELOPMENT FEE TABLE
Project: Robertson Commercial Pools Addition, Lot I, Block A
Date: 11/4/98
TOTAL AMOUNT DUE
FEES DUE PRIOR TO
COUNCIL
APPROVAL
Water Impact Fee $0.00 $0.00
(100% due prior to Council Approval)
Water Tap Inspection Fee $0.00
(100% due at Issuance of Water Meter)
Water Meter Fee (Domestic) $0.00
(100% due at Issuance of Water Meter)
Water Meter Fee (Irrigation/Fireline) $0.00
(100% due at Issuance of Water Meter)
Water Meter Deposit (Domestic) $0.00
(100% due at Issuance of Water Meter)
Irrigation/Fireline Meter Deposit $0.00
(100% due at Issuance of Water Meter)
Wastewater Impact Fee $0.00 $0.00
(100% due prior to Council Approval)
Wastewater Tap Inspection Fee $0.00:
(100% due at Issuance of Building Permit)
Utility Final Inspection Fee $0.00
(100% due at Issuance of Building Permit)
Park Fee $0.00 N/A
(100% due prior to Council Approval)
Roadway Impact Fee $1,514.95 $1,514.95
(100% due prior to Council Approval)
Street Light Fee N/A
(100% due prior to Acceptance of Project
Street Sign Fee N/A
(100% due prior to Acceptance of Project
Construction Inspection Fee N/A
tOTAL $1,514.95
TOTAL AMOUNT DUE PRIOR TO COUNCIL APPROVAL $1,514.95
ROADWAY IMPACT FEE CALCULATIONS
PROJECT: Robertson Commoz~l Pools Addition, Lot 1, Block A
DATE: 11/4/98
ROADWAY IMPACT
Service Area * 4
Category ** Indastxial
Land Use ** General Light Industrial
Building Size (Sq. Ft.) 4,764
Development Units ** 4.764
Vehicle Miles pet Development Unit ** 1.0~
Fee per Vehicle Mile *** $300
Roadway Impact Fee due = (Develop~nt Units) x
Vehicle Miles per Devdopment Unit) x (Fee per Vehicle Mile) = $1,514.9:5
* (Figure 2 - Roadway Impact Fee Study)
** (Table 3 - Roadway Impact Fee Study)
*** (Schedule 2, Page 3 - Roadway Impact Fee Study)