TR9302-CS 920630 Barton-Aschman Associates, Inc.
5485 Belt Line Road, Suite 199 Phone: (214)991-1900
Dallas, Texas 75240 Fax: (214} 490-9261
USA Metro: 263-9138
June 30, 1992
Ms. Pat Hickman
Traffic Safety Specialist
Texas Department of Transportation
P.O. Box 3067
Dallas, Texas 755221-3067
RE: Coppell -Traffic Light Synchronization II Project
Contract No. 582TLF6043
Dear Pat:
We are submitting on behalf of the City of Coppell, the Quarterly Progress Report for the
above referenced project. The attached report has been approved by the City's project
manager, Mr. Rey Gonzales.
If additional information or discussion is needed, please let me know.
Sincerely,
BARTON-ASCHMAN ASSOCIATES, INC.
Donald R. Glenn, P.E.
Senior Associate
cc: Mr. Rey Gonzales
Contract Number 582TLF6043
QUARTERLY TRAFFIC LIGHT SYNCHRONIZATION II REPORT
(Attach Additional Sheets As Needed)
1. City City of Coppell
2. Project Name Denton Tap Road
3. Reporting Period: From 3/30/92 to 6/30/92
4. Major Accomplishments this Reporting Period:
· Completed and subbmitted the "Before" study to the City and TxDOT.
· Began interconnect design for "closed-loop" signal system.
5. Major Problems or Delays this Reporting Period:
N/A
6. Is Work Progressing on Schedule (yes) (no) If no, explain:
Yes
7. Assistance Needed? (yes) (no) If yes, explain:
No
8. Other Information Pertaining to This Project/Program:
· Final PS&E for the signal system improvements are expected to be completed
by the end of July.
· Implementation is expecteed to take approximately 30~45 working days.