Loading...
TR9302-CS 920501 FILE COPY 2630 W. Freeway, Suite 242 Phone: (817)877-5803 Fort Worth, Texas 76102 Fax: (817) 877-3214 USA PROJECT STATUS REPORT DATE: May 1, 1992 PROJECT: Coppell TLS II BA No. 3311.07.01 PERIOD: March 26, 1 992 to April 27, 1 992 PREPARED BY: Kathi D. Mullins Work Completed this Period: 1. Quarterly Progress Report was submitted to TxDOT on March 30, 1992. 2. Reviewed 24-hour machine counts. 3. Determined existing intersection geometrics, lane usage, and link distances for computer input. 4. Collected 2-hour turning movement counts (TMC) during AM, Noon, and PM peak periods. 5. Conducted "floating car study" (travel time and delay study) for Denton Tap during AM, PM, and Noon peaks. 6. Determined signal phasing and timing for AM, PM, and Noon peak periods. 7. Simulated existing "Before" conditions and analyzed performance with TRANSYT-7F signal optimization/simulation program for each study intersection. 8. Calibrated TRANSYT-7F model travel time to observed travel times to be within a 20% of each other. 9. Submitted computer specifications to the for review on City on April 27, 1992. Work to be Completed next period: 1. Prepare "Before" study as per State requirements and submit two (2) draft copies. 2. Submit "Before" study to City for review on May 4, 1992. 3. Revise report, as needed and submit seven (7) copies of final report. 4. Determine local intersection traffic control needs. 5. Begin interconnect cable route design.