TR9302-CS 920330Barton.Aschman Associates, Inc.
5485 Belt Line Road, Suite 199 Phone: (214)991-1900
Dallas, Texas 75240 Fax: (214) 490-9261
USA Metro: 263-9138
March 30, 1992
Mr. Mike West
Traffic Safety Specialist
Texas Department of Transportation
P.O. Box 3067
Dallas, Texas 755221-3067
RE: Coppell - Traffic Light Synchronization II Project
Contract No. 582TLF6043
Dear Mr. West:
We are submitting on behalf of the City of Coppell, the Quarterly Progress Report for the
above referenced project. The attached report has been approved by the City's project
manager, Mr. Rey Gonzales. We are enclosing a copy of Form 20.102, Certificate of
Insurance, that is on file with the State for TLS II projects.
If additional information or discussion is needed, please let me know.
Sincerely,
BARTON-ASCHMAN ASSOCIATES, INC.
Donald R. Glenn, P.E.
Senior Associate
cc: Mr. Rey Gonzales
Ms. M. Shohre Daneshmand
Contract Number 582TLF6043
QUARTERLY TRAFFIC LIGHT SYNCHRONIZATION II REPORT
(Attach Additional Sheets As Needed)
1. City City of Coppell
2. Project Name Denton Tap Road
3. Reporting Period: From 2/66/92 to 3/30/92
4. Major Accomplishments this Reporting Period:
City Council approved the selection of Barton-Aschman Associates, Inc. to
perform engineering services on March 10, 1992.
· Project initiation meeting between City staff and Barton-Aschman was held on
Tuesday, March 24, 1992.
5. Major Problems or Delays this Reporting Period:
N/A
6. Is Work Progressing on Schedule (yes) (no) If no, explain:
Yes
7. Assistance Needed? (yes) (no) If yes, explain:
No
8. Other Information Pertaining to This Project/Program:
· Traffic volume data collection and travel time data collection will begin on
Tuesday, March 31, 1992.
· The "Before" study is expected to be completed by mid-April.
don\w~t382.r~p