Riverchase(3)-CS 880329 (2)COPPELL PUBLIC ~ORKS
MI~4ORANDUM
M~rch 29, 1988
TO:
FROM:
RE:
Steve Goram, Director of Public Works
Steven Morton, Chief Public Works Inspector
Status of MacArthur Blvd.
As per your request for a list of deficient items, I submit the
following:
1. None of the utility punch list items have been addressed. I
have had several meetings with Terra and Nathan Maier. Bobby
Harrell has assured me the items will be taken care of.
2. Landscape first median on MacArthur Blvd., south of Beltline.
The irrigation and landscaping materials were removed prior
to myself assuming project from Ginn, Inc.. To all intents
and purposes, Janet Vick of Nathan Maier instructed Allen
Johnston of CMA to remove plants, irrigation heads, and valves
from Beltline to the bridge. The plants were taken to the
Sunbelt Savings building. Irra Tech has possession of the
irrigation materials. In the last meeting with Bobby Harrell,
he said that he submitted landscape and irrigation plans to
Richard Diano, who has agreed with the plans. Terra has taken
out irrigation permits and has started cleaning out the median.
3. The intersection deviates from city standards by using 6 cm
brick instead of 8 cm brick. The wheelchair ramps on the north
side are radial, not full cord like the wheelchair ramp on
the south side. These deviations were on their approved plans.
4. One of the manholes for our 24" water valve is still buried.
5. The signal pole hit by truck will need to be replaced. It
is my understanding that this is covered by truck's insurance.
It will take 4-6 weeks to receive delivery after the insurance
company issues check to Sharrock Electric.
Ail these items have been called out to them throughout the
construction process and are on the final punch list from the final
walk through.
SMM/sm