Riverchase(3)-CS 870811MEMORANDUM August !i, Ig87 TO: FROM: VIA: RE: Alan Ratliff, City Manager Steven M. Morton, Chief of Land Development Steve Goram, Director of Public Works Beltline- MacArthur Intersection Update The opening of Beltline/ MacArthur intersection has been delayed until the week of August 17, 1987 due to the following: · Two weeks lost in design changes (drafting errors). · Rescheduling and rebidding the installation of buttons/stripes. · Railroad crew had emergency repairs in Tyler. As of this date, the following have been accomplished: · Plans have been corrected and approved. · Bids received and approved by Terra. · Contractors earliest start date is August 17, 1987. · Railroad crew to return to the site this week. The completion should take place the week of August 17, 1gB7. SMM/sm