December 26, 2002
Mr. Kenneth M. Griffin, P.E.
Director of Engineering and Public Works
City of Coppell
255 Parkway Blvd.
Coppell, Texas 75019-4409
ae~
Sandy Lake Road Reconstruction
Coppell Project #: ST 93-02
Kimley-Horn Project #: 06940600
DWU Project #: 98-3llf
Dear Mr. Griffin:
During installation of the storm sewer on the referenced project, the proposed storm sewer
system was modified at the direction of the City to accommodate utilization of the existing storm
sewer system. These modifications required the utilization of several additional concrete collars
for connections between storm sewer lines. As a result, EBCC submits the following items for
inclusion on the next change order:
Item Description Quantity Unit Price Extension
CONCRETE COLLAR FOR 21" RCP 8.00 EA $400.00 $3,200.00
CONCRETE COLLAR FOR 24" RCP 1.00 EA $445.00 $445.00
CONCRETE COLLAR FOR 36" RCP 8.00 EA $530.00 $4,240.00
Total $7,885.00
Your attention regarding this matter is greatly appreciated. This work required an additional ten
(10) calendar days to complete. If you have any questions regarding this information, don't
hesitate to contact our office.
Sincerely,
C°nstL~!ti°n
Robert D. Weber
Project Manager