Sherwood Park 2-CS 840814GINN, INC.
August 1~, 1984
CONSULTING ENGINEERS
GENERAL HOHES
15301 Dallas Parkway, #1020
Dallas, TX 75248
Attn: Skip Hynek
Re: Sherwood Park I
Dear Skip:
As per our telephone conversation on August 10, 1984, the one-year maintenance
bond submitted by Crawford Utilities should be dated August 1, 1984. The date
of July 13, 1984, submitted on the first bond does not reflect the two week
grace period, and as you recall, the offsite drainage channel had not been
completed as of that date.
Also, the sanitary sewer main on Kirkland Drive is still show/rig signs of
infiltration. Your prompt attention in this matter would be appreciated
and will help expedite the final acceptance letter to the above referenced
project.
Sincerely,
GINN, INC./'~
Randy Fleming
RF:sr
cc: Ron Ragland
Steve Goram
Jeff Hawkins