Shadow Woods-CS 891114 (2)DATE:
TO:
FROM:
COPPELL PUBLIC WORKS
November 14, 1989
Dale Jackson, Building Official
Russell R. Doyle, City Engineer
Shadow Woods Addition- 2 Models
Shadow Ridge Addition lA- 3 lots
Request for Building Permit Prior to
Infrastructure Acceptance
TO & Circulate off
~' ,
Steve Stolte has requested that building permits be issued for
subject lots prior to the completion and acceptance of the
infrastructure. He indicated that you requested a notification
from this department and the Fire Marshal.
As we understand, the Fire Marshal has requested a hard surface
access and city water be available.
As Larry Davis has indicated to the Developer's representatives,
we must have water and sewer systems in and backfilled, all in
compliance with approved construction drawings, etc. and no doubt
per the Fire Marshal's requests a hard all-weather surface is
required from the Coppell Road to each building/house for the
Shadow Woods Addition request (see attached check list for detailed
items).
As has been discussed, the other necessity is to have the concrete
street approaches to Coppell Road in place and cured out before any
house contractor access is permitted into the Shadow Woods
Addition.
Therefore, if these conditions are satisfied, then we would have
no objections for subject request to be granted. Of course, the
details and process is subject to Larry Davis' review and approval
as the Developer accomplishes what is required so that there is no
adverse burden placed on the City's field inspection operations,
etc.
Please let
Larry Davis
Thank you.
us know if
or myself
you have any questions and please contact
for any other control or policy questions.
RRD/bb
xc: Steve Goram, Director of Public Works
Larry Davis, Construction Inspector
Steve Stolte, Centex, Inc.
¢eP¥
CITY OF COPPELL
Public Works Department
Items to include but not be limited to the following before early
building permits can be issued:
Water Main Installation
Adjust Valves
Adjust Fire Hydrant
Set Water Meter boxes
Mark Curb and Gutter
Sewer Main Installation
Adjust Sewer Manholes
Adjust Sewer Clean Outs
Mark Curb and Gutter
Backfill
Proper Backfill in Right-Of-Way of Ail Streets
Proper Backfill in All Alleys
Inlet Construction
Complete Construction of All Inlets
Complete Backfill Around Inlets
BPERMITS.CLD