SC-Coppell MSE-CS 920626COPPELL PUBLIC WORKS DATE: TO: FROM: RE: June 26, 1992 Steven G. Goram, Director of Public Works Rick Wieland, Parks & Recreation Manager Coppell Middle School 1992 Ballfield Improvement (Tickler 6/23/92) Staff has experienced an usually high amount of rainfall in the last several weeks, restricting the finish grading of the sewer line at the Middle School site. I would anticipate that a window of hot, dry weather should be in effect within the next several weeks. Staff will then complete that project accordingly. Staff will continue to monitor this matter and update you on its completion by July 21, 1992. RSW/dm BALLIMPV. RSW