SC-Coppell MSE-CS 920522COPPEL~ PUBLIC WORKS
DATE:
FROM:
May 22, 1992
Steven G. Goram, Director of Public Works
Rick Wieland, Parks & Recreation Manager~
Coppell Middle School - 1992 Ballfield Improvements
(Tickler 5/21/92)
Since the date of my last memorandum, staff monitored the
completion of the installation of overhead doors at the
restroom/concession facility and the pouring of the concrete pad at
the sewer lift station pump. The finish grading of the sewer line
will be completed as soon as the moisture level of that area is
dry. Staff will work to complete that item within the next 2-3
weeks as weather allows.
Staff will monitor this matter and update you on its progress by
June 23, 1992.
RSW/dm
MIDDLE3.RSW