July 7, 1992
Steven G. Goram, Director of Public Works
Rey Gonzales, Streets Superintendent~
Proposed Sidewalk on Coppell Road/Estimate
(Tickler 7/10/92)
We currently do have the funding to purchase the necessary
materials for the asphalt portion of sidewalk from Edinburgh to
Halifax. The time to accomplish this project is not easily
attainable with the current work demand in the street maintenance
function of my shop. It can be done but other outstanding projects
would be placed on hold till the sidewalks (concrete and asphalt)
could be completed. The two projects would take approximately 30
to 45 days to complete.
Next status 7/29/92
RG/dg