SS9901-CS050301CONSTRUCTION COMPANY l ] 051 Grissom Lane Dallas, Texas 75229 972-484-4344 tele 972-484-4223 fax March 1, 2005 Mr. Kenneth M. Griffin City of Coppell 255 Parkway Boulevard Coppell, Texas 75019 Reference: Deforest & Sandy Lake Lift Station Coppell, Texas SubjGct: Change in Conditions Dear Mr. Griffin: Can-Fer Construction Company has encountered a change in conditions at the work site that was not part of the bidding process. We based our bid on the fact that there would be no other contractors working on our work site as delineated by the contract documents. The other contractor has forced us to double and triple handle excavated material because we do not have access around our excavation. Can-Fer Construction Company is in the process of quantifying the impact in cost and in time for this change in condition. Sincerely yours, Todd C. Hoff Project Manager TCH:dma cc: Charles Ferrara Rick O'Dell, Construction Inspector