Stoneleigh P2-CS020206T H E C I T Y 0 F
February 6, 2002
Mike Daniel, P.E.
Nathan D. Maier Consulting Engineers, Inc.
Two Northpark, Suite 600
8080 Park Lane
Dallas, TX 75231
Stoneleigh at Riverchase II
Final Acceptance
Dear Mike:
A final inspection of paving and utilities for the referenced project has been confirmed by
representatives of the City of Coppell.
The two-year maintenance bonds and as-built drawings have been received fi.om the contractor.
Maturity on the bonds will be two years fi.om the date of this letter.
CC:
Ken Griff'm, Director of Engineering
Rhonda Brothers, Engineering Secretary
Glenn Hollowell, Director of Public Works
Greg Jones, Chief Building Official
Travis Crump, Fire Marshal
Keller Webster, Project Mgr., Spring Valley Construction