Town Center L2B3-CS050302 T H E C I T Y O F
COPPEIJ£
March 2, 2005
Scott Caruthers, P.E.
Dowdey, Anderson & Associates
5225 Village Creek Dr
Plano TX 75093
Town Center, Lot 2 Block 3 (Village at Town Center)
Final Acceptance
Dear Mr. Caruthers:
Representatives of the City of Coppell have confirmed a final inspection of paving and utilities
for the referenced project. The two-year maintenance bonds and as-built drawings have been
received from the contractor. Maturity on the bonds will be two years from the date of this
letter.
You may notify the MS4 (City of Coppell) at any time during the two-year maintenance period if
stabilization of the site per the SWPPP permit can be demonstrated. If so, complete and submit a
Notice of Termination (NOT) to discontinue coverage under the SWPPP permit.
A follow-up inspection of the facilities will be conducted prior to the lapse of the two-year bond
period. If any punchlist items are noted at that time, you will be contacted to make repairs.
Thanks for your cooperation.
Fax: (972) 304-3570
CC:
Ken Griffin, P.E., Director of Engineering & Public Works
Keith Marvin, P.E., Civil Engineer
~enn Hollowell, P.E., Assistant Director of Public Works
Greg Jones, Chief Building Official
Tim Oates, Fire Marshal
Glen A. Hinckley, Centurion Eagle Inc.
Brad Fowler, HCI General Contractors