Villages of CC 6-CS 941101 (2) The City With A Beautiful Future
November 1, 1994 ~/~-/
Tipton Engineering ~
6330 Beltline Road Suite C ~
Garlan!,~Texas 75043 f ~
RE: ¥111a~,es of Cottonwood Creek Section VI.~
Deve ~'
P,O, Box 478
Coppell, Texas 75019
214-462-0022
Dear Sir:
Enclosed is a copy of the City of Coppell Development Fee Assessment list, along with a copy of
the Development Fee Calculations for the Villages of Cottonwood Creek Section VI addition.
Please make payment to the City of Coppell in the amount of $275.301.10 and forward it to Alan
Johnson, Finance Director, along with a copy of the Fee Assessment List. A copy of the Engineer's
estimate or contract for this project will need to be provided to our department so the construction
inspection fee can be verified.
Providing a copy of'your paid receipt to our office will help us to verify payment of the required
fees and insure a successful beginning of this project. We look forward to working with you on this
project. If you have any questions, please do not hesitate to contact me.
Sincerely,
Kenneth M. Griffin, P.E.
Asst. City Manager/Dir. Public Works/City Engineer
CCi
Alan Johnson, Finance Director
Greg Jones, Building Official
Doug Stevens, Engineering Technician
Howard Pafford, Utilities Superintendent
Rey Gonzales, Street Superintendent
Rick Wieland, Parks and Recreation Manager
CITY OF COPPELL
DEVELOPMENT FEES
Date:
Project:
November 1, 1994
Villages of Cottonwood Creek Section VI
TOTAL AMOUNT DUE
.FEES DUE PRIOR TO
COUNCIL
APPROVAL
Water Impact Fee
(100% due prior to Council Approval)
Water Tap Inspection Fee 18,500.00 -0-
(100% due at Issuance of Water Meter)
Wastewater Impact Fee
(100% due prior to Council Approval)
Sewer Tap Inspection Fee 18.400.00 -0-
(100% due at Issuance of Building Permit)
Utility Final Inspectkm Fee 9,200.00 -0-
(100% due at Issuance of Building Permit)
Water Meter Fee (Domestic) 4,094.00 -0-
(100% due at Issuance of Water Meter)
Water Meter Deposit (Residential) 5,520.00 -0-
(100% due at Issuance of Building Permit)
Water Meter Fee (Irrigation & Fire) 189.10 -0-
(100% due at Issuance of Water Meters)
Irrigation Meter Deposit 35.00 -0-
(100% due at Issuance of Water Meters)
Street Sign Fee 4,634.32 -.0-
(100% due prior to Acceptance of Project)
Street Light Fee * inti~rmation not -0-
(100% due prior to Acceptance of Project) available
Park Fee
(50% due prior to Council Approval) $13,800.00 $13,800.00
(50% due prior to Issuance of Building Permit)
Street Escrow (100% due prior to Council Approval) 53,901.10 53,901.10
Construction Inspection Fee need submittal of -0-
(2% of Project Cost dt, e prior to Preconstr. Mtg.) contracts
TOTAL $335.873.52 $275,301. l0
TOTAL AMOUNT DUE PRIOR TO COUNCIL APPROVAL
* This t~e cannot b~ assessed until alter TU Electric submits the lighting plan t~ar the proposed project. Once the plan
is submitted, $292.60 per light will be assessed.
COPPELL PUBLIC WORKS
MEMORANDUM
DATE:
TO:
FROM:
RE:
November 1, 1994
Mike Martin, E.I.T.
Howard Pafford, Utilities Superintendent
Development Fees for Villages of Cottonwood Creek Section VI
The following fees
referenced project.
Water Impact Fee:
18~- 5/8" x 3/4"
should be assessed and collected on the above
Domestic Meter/s = I~ESU's
Irrigation Meter/s = ~ ESU's~
su,s 65o.oo ea = ]30'O0
Total ~
100% due prior to Council approval of the final plat.
Wastewater Impact
184 - 5/8" x 3/4" Domestic Meter/s =
Total 184 ESU's @ $450.00 ea =
184 ESU's
$ 82,800.00
100% due prior to Council approval of the final plat.
Water Tap Inspection Fee
185 Connections ~ $100.00 each = $ 18,500.00
100% due prior to issuance of building permit for residential. (Or in
the case of multi-family, commercial, retail, industrial, fee is due
prior to issuance of meter).
Sewer Tap Inspection Fee
184 Connections @ $100.00 each = $18,400.00
100% due prior to issuance of building permit. (Residential only)
Development Fees
Page 2
Utility Final Inspection Fee (All Development)
184 lots @ $50.00/10t = $9,200.00
100% due prior to issuance of building permit.
Water Meter Fee (Domestic)
184 - 5/8" x 3/4" Domestic Meters @ 22.25 ea = $4,094.00
100% due prior to issuance of building permit for residential only.
Ail other development fees are due prior to issuance of meter/s.
Water Meter Fee (Irrigation)
i - 2 Irrigation Meter/s @ $ 189.10ea
100% due prior to issuance of water meter/s.
= $ 189.10
Water Meter Deposit (Residential)
184 Meters ~ $30.00 ea = $5,520.00
100% due prior to issuance of building permit.
Irrigation Meter Deposit N/A
1 Meters ~ $35.00 ea = $35.00
100% due prior to issuance of water meters.
Note: These calculations do not include water fees for
meters. Sizes were not available.
irrigation
Development Fees
Page 3
Park Fee
For those developments having preliminary plat approval prior to June
23, 1992 the following assessment is determined:
Residential Lots at $150.00 each
Units (Multi family) at $75.00 each = $
50% of the amount specified above shall be paid by the Developer;
prior to Council approval of final plat.
50% remaining shall be paid by the Builder at such time as a building
permit is issued.
For those developments having preliminary plat approval after June 23,
1992 the following assessment is determined:
Residential Lots at $350.00 each = $
Units (Multi-Family) at $350.00 each = $
50% of the amount specified above shall be paid by the Developer prior
to Council approval of final plat.
50% remaining shall be paid by the Builder at such time as a building
permit is issued.
For those developments having preliminary plat approval after October
26, 1993 the following assessment is determined:
.-l~4_Residential Lots within Park Zone 1 at $1,285.00
~'"~'P~ Units (Multi-Family) at $1,285.00 each = $
each
100% of the amount specified above shall be paid by the Developer
prior to Council approval of final plat.
Please advise the Developer of these fees and due dates.
If you have any questions regarding these assessments please advise.
Development Fees
Page 4
Street Lighting Fee
Shall
Note:
be assessed and paid prior to final acceptance of project.
This fee cannot be assessed until after TU Electric submits
the lighting plan for the proposed project. Once plan is
submitted $292.60 per light will be assessed.
Street Signs Fee
See attached Street Sign Assessment sheet.
100% due prior to final acceptance of project.
Development Fees
Page 5
STREET SIGN ASSESSMENT
for
The following assessment is being made in accordance with the City of
Coppell Subdivision Ordinance Appendix A Chapter VIII A. The
following cost of those sign materials required are based on current
pricing which is reviewed on a regular basis.
SIGN
No Parking $53.10
Speed Limit $63.54
Yield $58.56
Stop $65.12
Street Name $11.60
Stop & Street Combo $96.85
OTHER
No outlet{30"Diamond 63.54
No outletfblade) 11.60
UNIT PRICE
QUANTITY EXTENDED PRICE
44 $2,795.76
16 1,549.60
4 254.16
3 34.80
* Cost breakdowns may be
request.
TOTAL $4,634.32
obtained from Public Works by written
VILLAGESVI Revised 1/14/94