Northlake WE P1-6-CS040115COPPELL
January 15, 2004
Jemy Daniels
4D Construction
11200 Old Seagoville Rd
Balch Springs TX 75180
Drainage Improvements at 775 Pelican Ln
Final Acceptance
Dear Mr. Daniels:
Representatives of the City of Coppell have confirmed a final inspection of the referenced project.
The two-year maintenance bond and as-built drawings have been received fi.om the contractor.
Maturity on the bond will be two years from the date of this letter.
Sincerely,
Rick O'Dell
Construction Inspector
Office Phone: (972) 304-7090
Fax: (972) 304-3570
CCi
Ken Griffin, Director of Engineering & Public Works
Rhonda Brothers, Engineering Secretary
~Glenn Hollowell, Director of Public Works
Donald Brewer, 775 Pelican Ln, Coppell TX