Loading...
Vista Point II 3-7-CS050603 (2)T H IE C I T Y 0 F COl'FELL £ June 3, 2005 Mr. Erik M. Hauglie, P.E. Pacheco Koch Consulting Engineers 8350 N. Central Expressway, Suite 1000 Dallas, TX 75206 RE: Vista Point II (Infrastructure), Lots 3-7, Block A Fee Assessment Letter Dear Mr. Hauglie: Enclosed is a copy of the City of Coppell Development Fee Assessment table, along with a copy of the Development Fee calculations for the referenced development. The only fees assessed for the site at this time are associated with the installation of the fire meters. Roadway Impact Fees and Water and Sewer Impact Fees associated with domestic and irrigation water meters will be assessed as each individual lot is developed. Please note that the Texas Legislature, under Senate Bill 243, delayed the collection of Water and Sewer Impact Fees until the issuance of a Building Permit. Please provide a copy of the Engineer's estimate or contract for the work in your plans to our office so the 2% & 4% construction inspection fee can be verified. The construction inspection fees must be paid prior to the scheduled pre-construction meeting and issuance of a Construction Development Permit. The additional fees for water and sewer taps, water meters, and utility inspection fees need to be paid by separate check at the new Public Works Service Center, 816 S. Coppell Road. Meters will be ordered when those fees are paid. Appropriate payment of the required fees will help insure a successful beginning of this project. We look forward to working with you on this project. If you have any questions, please contact me. Sincerely, Charlene La Mattitia, E.I.T. Graduate Engineer Jennifer Armstrong, Finance Director Mary Beth Spletzer, Admin Tech, Building Inspections ~Glenn Hollowell, Assistant Director of Public Works Greg Jones, Chief Building Official Brad Reid, Director of Parks and Recreation DEVELOPMENT FEE TABLE Project: Vista Point H (Infrastructure), Lots 3- 7, Block A Date: 6/1/2005 TOTAL AMOUNT DUE FEES DUE PRIOR TO FILING PLAT Water Impact Fee $700.00 (100% due at Issuance of Building Permit) Water Tap Inspection Fee $100.00 (100% due at Issuance of Water Meter) Water Meter Fee (Domestic) $0.00 (100% due at Issuance of Water Meter) Water Meter Fee (Irrigation/Fireline) $8,342.30 (100% due at Issuance of Water Meter) Water Meter Deposit (Domestic) $0.00 (100% due at Issuance of Water Meter) Irrigation/Fireline Meter Deposit $60.00 (100% due at Issuance of Water Meter) Wastewater Impact Fee $0.00 (100% due at Issuance of Building Permit) Wastewater Tap Inspection Fee $0.00 (100% due at Issuance of Building Permit) Utility Final Inspection Fee $0.00 (100% due at Issuance of Building Permit) Park Fee $0.00 $0.00 (100% due prior to Filing Plat) Roadway Impact Fee $0.00 $0.00 (100% due prior to Filing Plat) Street Light Fee Information not Available (100% due prior to Acceptance of Project) Il Street Sign Fee Information not Available (100% due prior to Acceptance of Project) II Construction Inspection Fee Information not Available (100% due prior to Start of Construction) It TOTAL $9,202.30 TOTAL AMOUNT DUE PRIOR TO FILING FINAL PLAT $0.00 DEVELOPMENT FEE WORKSHEET PROJECT: Vista Point H (Infrastructure), Lots 3-7, Block ~l DATE: 6/1/2005 Water Impact Fee: Domestic Meter(s): 0 = 0 Irrigation Meter(s): 0 = 0 0 = 0 Fireline Meter(s): 2 - (1) 8"; (1) 10" = 2.5 Total #: 2.5 ESU's @ $280.00 ea. (Due prior to issuance of building permit) Water Tap Inspection Fee: Total #: 2 Connections @ $50.00 ea. (Single family due prior to issuance of building permit) (All other developments due prior to issuance of meter) Domestic Water Meter Fee: Total #: 0 Domestic Meter(s) @ $0.00 (Single family due prior to issuance of building permit) (All other developments due prior to issuance of meter) Irrigation/Fireline Water Meter Fee: Total #: 0 Irrigation Meter(s) @ $0.00 Total #: 1 Fireline Meter(s) @ $3,371.21 Total #: 1 Additional Fireline Meter(s) @ $4,971.09 (100% due prior to issuance of water meters) Domestic Water Meter Deposit Fee: Total #: 0 Meter(s) @ $30.00 ea. (100% due prior to issuance of water meters) Irrigation/Fire Meter Deposit Fee: Total #: 2 Meter(s) @ $30.00 ea. (100% due prior to issuance of water meters) Wastewater Impact Fee: Total Domestic Meters ESU's: 0 (Due prior to issuance of building permit) @ $280.00 ea. Wastewater Tap Inspection Fee: Total #: 0 Connections @ $50.00 ea. (100% due prior to issuance of building permit) Utility Final Inspection Fee (All developments): Total #: 0 Lots @ $80.00 ea. (100% due prior to issuance of building permit) ESU's ESU's ESU's ESU's $700.00 $100.00 $0.00 $0.00 $3,371.21 $4,971.09 $0.00 $60.00 $0.00 $0.00 $0.00 Park Fee (For Residential Developments Only): Page 1 DEVELOPMENT FEE WORKSHEET * Preliminary plat approved: After June 23, 1992 0 Single-family @ $0.00 per lot 0 Multi-family @ $0.00 per unit (100% paid prior to Council approval of final plat) $0.00 $0.00 $0 O0 Information not Available Roadway Impact Fee: (See attached fee calculations) Street Lighting Fees: Assessed for lighting in the City's right-of-way. This fee cannot be assessed until after T.U. Electric submits the lighting plan for the proposed development. Once the plans are submitted, $292.60 per light will be assessed. (100% due prior to final acceptance of development) Street Sign Fees: Assessed for signage in the City's right-of-way. (See attached fee calculations if applicable) Information not Available Construction Inspection Fees: A copy of the development contract must be submitted for assessment. The contracts should indicate the cost to construct the improvements that are inspected by the Engineering Department. (2% of development cost required for private improvements) (4% of development cost required for public improvements) Information not Available Page 2 ROADWAY IMPACT FEE CALCULATIONS PROJECT: DATE: Vista Point H (Infrastructure), Lots 3- 7, Block ,4 6/1/2005 ROADWAY IMPACT FEE: Service Area * 2 Category ** Commercial Land Use ** 0 Data Not Available 0 Development Units ** 0.00 Vehicle Miles per Development Unit ** 0 Fee per Vehicle Mile *** $300 Roadway Impact Fee due = (Development Units) x (Vehicle Miles per Development Unit) x (Fee per Vehicle Mile) = $0.00 * (Figure 2 - Roadway Impact Fee Study) ** (Table 3 - Roadway Impact Fee Study) *** (Schedule 2, Page 3 - Roadway Impact Fee Study)