Waterside E P3-CS 950825DATE= FROM= RE= COPPELL UTILITIES MEMORANDUM Inspector August 25, 1995 Larry Davis, Constrution Howard L. Pafford, Utilities /Sewor Walkthrough Utilities personnel performed a follow up walk thru on the above referenced project and found that all punchlist items have been corrected. If you have any question regarding this matter,please advise. HLP/hp DATE: TO: FROM: RE: COPpELL UTILITIES MEMORANDUM August 16, 1995 Larry Davis, Construction Inspector Howard pafford, Utilities Superintendent Final Walk-Through for Waterside Estates ,hase III Utilities personnel performed a walk-thru on the above referenced project this morning and the following items were found to be del icient; ~ Lot 14 Blk. H-Lot cleanout missing. / Inflow coming in manhole at Mariners Ct. and Cove Lot 11 Blk. G-Water service leak. ~ Lot 5 Blk. H-Replace meter setter. ~/~install brass elbows on all 2" blowoffs. ~.~_ ~ *~ Main line valve missing at Parkway and MacArthur. ~ Lot 8 Blk. G-Repour concrete pad for lot cleanout. Please ensure that each of these items are corrected prior to final acceptance of this project.