ST9304-SY 860108ALIGNMENT STUDY OF BELTLINE ROAD
FROM COPPELL CITY LIMITS TO IH-35E
PROJECT #490-402
DALLAS COUNTY
~i .......
January 1986
ALIGNMENI STUDY
OF
BELILINE ROAD
FROM
COPPELL CIIY LIMIIS TO IE-35E
PROJECT #490-402
DALLAS COU~;TY
Albert H. Halff Associaces, Inc.
Engineers and Scienrists
January 1986
DAVID G. FOX,
COUNTY JUDGE
JIM JACKSON,
COMMISSIONER, DISTRICT NO. i
_. NANCY E. JUDY,
COMMISSIONER, DISTRICT NO. 2
JO[t~ ~ILEY PRICE,
COMMISSIONER, DISTRICT NO. 3
CHRIS V. SEMOS,
COMMISSIONER, DISTRICT NO. 4
J. W. BRYA~, P.E.,
DIRECTOR OF PEBLIC WORKS
ii
ALBERT H. IL LFF ,s ;SOCIATES. INC.
ENGINEERS AND SCIENTISTS
P~lic Works Department
Dallas County
-- 161 Com~rce Street
Dallas, TX 75207
__ Att: Mr. J.W. B~an, P.E.,
Director of Public Works
Re: Beltline Road, Paving and Draioage Improvements from Coppell City
-- Limits to IH-35E, Project 490402
Gentlemen:
Transmitted herewith is an Alimnment Study for Beltline Road
Coeoell City Lim{ts to IH 35~, authorized by the Commissioners Court in
Court Order #85-1914, dated December 9, 1985.
We trust that this report will be of assistance to the County in
evaluating the engineering and design features of the two alternative
-- alig~ents. Of the two routes analyzed, the southern route is clearly
superior, safer, less costly, and could be completed in one year less
than the existing route. The southern route will accrue greater benefits to
._ the citizens of Carrollton, Coppell and Dallas County.
Please contact us if further info~ation is needed. We are proceed
with the surveying of the existing right-or.ay, We are ready to proceed
-- with the design as soon as we are advised of the route selected.
Respectfully submitted,
-~ERT R. ~LFF ASSOCIATES, INC.
Io ~ovoa~ P.E.,
-- ~resident
/fw
Attachment
TABLE OP CONTENTS
I, DESCRIPTION OF PROJECT
Iio INVENTORY OF EXISTING CONDITIONS
A. Existing Right-of-way
B. Street Crossings and Intersections
C. Access Points
D. Railroad Crossings
E. River and Channel Crossings
F. Existing Utilities
G. Traffic
H. Environmental Considera=ions and Role of
Regulatory Agencies
IIi. DESIG~ CRiIERIA
A. Iypical Cross Section
B. Design Speed
C. Relation tc 100 Year Flood
IV. ALTERNATIVE ALiGNf~NTS
A. Present Location
1. Right-of-way Requirements
2. Embankment Required
3. Road Crossings
4. Bridges and Drainage Structures
5. Utilities
6. ~ortb Access Points
7. Construction Phasing and Detouring Required
8. Construction Timing
9. Construction Cost
iv
B. SOUTHERN ROUTE (West of Hutton Drive)
1. Right-of-way Requirements
2. Embankment Required
3. Road Crossings
4. Bridges and Drainage Structures
5. Utilities
6. Worth Access Points
7. Construction Phasing ar~ Detouring Required
8, Construction Timing
9. Construction Cost
V. EV~UATION A~D RECOMMENDATIONS
A. Safety
B. DraRnage Consideration
C. Construction Timing
D. Cost
E. Legal Aspects
F. Recommendations
VI. FIGURES
VII. APPENDICES
1. Design Data
2. Hydraulic Data - Existing Alignment
3. Cost Estimate - Existing Alignment
4. Hydraulic Data - Southern Route
5. Cost Estimate - Southern Route
6. List of Attendees, November 12, 1985 Meeting
7. Geotechnieal Letters
LIST OF T~kBLES
Table No. Description Page No.
I Bridges Alcng the Elm Fork oi the Trinity
River 6
2 Standard Roadway Design Griteria 11
3 Elm Fork Water Surface Elevations -
Sicgle Model Analysis 18
4 Elm Fork Water Surface Elevations -
Split Flow Analysis 19
5 Construction Timing - Existing Alignment 24
6 Estimated Construction Costs -
Existing Alignment 25
7 Construction Timing - Southerm Route 34
8 Estimated Construction Costs -
Southern Route 35
9 Summary of Estimated Costa -
Both Alternative Alignments 36
vi
LIST OF FIGURES
Figure No.
I Prcper~y Ownership Map
2 Access Points for North Property Owners
3 Proposed Roadway Cross Section
4 MacArthur Boulevard Profile
5 Prcposed Bridge Profiles - Existing Alignment
6 Sequence of Construction Diagram
7 Layout of Proposed Southern Route
8 Luna Road Profile
9 Proposed Bridge Profile - Soutbero Route
!0 Southern Rcute- Bridge Layout
Il Year 2000 Iraffic Projection
12 Typical Beltline Road/St. Louis & Southwestern Railroad
vii
DESCRIPTION
I, DESCRIPTION OF PROJECT
Proposition Two of the Dallas County, Texas 1985 Bond Program provided
funding to improve Beltline Road from Denton Tap Road in Coppell to
Interstate Highway 35E in Carrollton. The County staff bas divided the
preparation of plans, specifications and construction documents for this
project into two design contracts. For the easterly porticn, Dallas County
contracted with Albert H. Halff Associates, Inc. to perform an alignment
study and Cc provide the preliminary amd final design plans, specifications
and contract documents. The Halff Associates contract covers the segment
between the Coppell City limits on the west and IH-35E on the east. The
proposed improvements include the raising of Beltline Road out of the 100-
year flood plain, construction of a 4-lane-divided major thoroughfare with
provision for adding two additional lames at some future date, and construc-
tion of new 6-lane divided bridges over Hutton Branch and the Elm Pork of
the Trimity River. At this time, the County has not yet selected an en-
gineering consultant for the preliminary and final design of the Beltline
Road improvements from the city limits of Coppell west to Denton Tap Road.
This report is a summary of the information gathered in the analysis of
slternative alignments of Beltline Road. The Report discusses the existing
conditions in the roadway corridor, and the feasibility of constructing the
improved Beltline Road within the existing right-of-way or along an alterca-
tire route approximately 600 feet south of the existing roadway. The report
includes discussion of design issues ~est of the Coppell city limit because
the southerly route is proposed to rejoi, n the existing Beltline Road align-
ment at a point west o£ Moore Road within the city limits of Coppell.
2
INVENTORY
Ii. INVENTORY CF EXISTING CONDITIONS
The Beltline Road right-of-way, from IR-35E to the Coppell City limit
line, varies in width from 90 feet to 120 feet. The right-of-way is south
of and adjoins the right-of-way of the St. Louis and Southwestern Railroad
(S.L.&S.W.R.R.) The railroad right-of-way varies from 100 to 150 feet in
width. At this time detailed property surveys have not Been completed and
therefore, the exact dimensions of the Beltline right-of-way have not yet
been determined.
A property ownership map has been prepared and is included on Figure 1.
As ~bown on Figure 1, the only property owner adjacent to Beltline Road on
the north side is the S.L.&$.W.R.R.
Based on present planning, there will be two major street intersections
on Beltline Road within the City of Carrollton and three major street inter-
sections within the City of Coppell.
In the City of Carrollton, Hutton Drive and Luna Road will intersect
Beltline Road. Hutton Drive has been designated by the City of Carrollton
as a 4-lane divided major thoroughfare, which will intersect Beltline Road
and end at that poimt. Luna Road ~s designated on the City of Carrollton's
Master Thoroughfare Plan as a 6-lane divided thoroughfare. The Thoroughfare
Plan shows Luna Road crossing ~he S.L.&S.W.R.R. at grade and continuing
north to IH-35E. At IR-35E Luna Road will connect with an existing segment
of Luna Road on the east side of IH-35E.
In the unimcorporated area, Ledbetter Road, a small county road, within
the floodway of the river, connects to Beltline Road just west of the Elm
Fork of the Trinity River.
In the City of Coppell, MacArtbur Boulevard is planned as a 6-lane
divided major thoroughfare. MacArtbur is planned to extend north of
Beltline Road, crnssing the S.L.~S.W.R.R. at grade and continuing to Sandy
Lake Road. Moore Street presently crosses the S.L.&S.W.R.R. and ties to
Beltllne Road. Mockingbird Lane presently stops north of the S.L.&S.~.R.R.
The S.L.&S.W,R.R. is 5 to 7 feet higher than the proposed grade of
Beltline Road, and therefore, the Luna Road amd MacArthur Bonlevard cros-
sings are critical issues in the design of the Beltline Road improvements.
There are four private points of access from Beltline Road for property
owners north of the S.L.&S.W.R.R. These include: (1) access to a concrete
batch plant; (2) acces~ to a wrecking yard; (3) access to a gun club, and
(4) an access point used to bring fill into an area north oi the railroad.
The points of access are shown on Figure 2. All four access points cross
under the railroad tracks at existing drainage structures and are subject to
flcoding. We have discussed the crossings with Mr, Dave Andrews, Area
Engineer, of the S.L.&S.W.R.R. Company. Mr. Andrews stated that only two
owners have obtained permits for private crossing of the railroad namely
4
Mr. Ihompson, the owner of the Wrecking Yard immediately west of the Elm
Fork, and the Gun Club i.m~d~ately east of the east overflow swale.
Beltline Road crosses a S.L.&S.W.R.R. spur track immediately west of
Hutton Drive. This spur track will require modification in the reconstruc-
tion of Beltline Road. The track will be raised and a new railroad crossing
with signals installed to meet safety standards will be required.
There are two major dra~naseways which cross Beltline Road east of the
Coppell city lizit. Ihese are the Elm Fork of the Trinity River, and
Hutton Branch. The Elm Fork of the Trinity River is a major stre~ with a
peek !G0-year fully developed flow rate, as determimed by the U. S. Army
Corps of Engineers, of 55,800 cubic feeg per second (cfs). Major bridge
structures w~ll be required to cross the Elm Fork Floodway. Table I sum-
mar{zee the bridges and drainage areas at other crossings near the Beltline
Road project.
Hutton Branch is a major stream within gke City of Carrollton with a
peak 100-year fully developed flow ra~e of approximately 12,000 cfs. Again,
a bridge structure will be required at Rutton Branch.
DuriDg floods both streams spread over the flo~ plain and an analysis
must be u:ade tc assure tha~ the improved Beitlime Road is se~ above ~he
flood levels. Long stretches of ~he existing Beltline Road have been peri-
odically over topped by flood waters. ~he most recent flood event that
TABLE 1
BRIDGES ALONG ~HE ELM FORK OF THE IRi~IIY RIVER
I LOCATION !
I Valle)' View I 710.50 I 140 I 1,400 i 13,361
I I 7ii .50 I I i
I J ___i ............ J l .........
{ Existin§ { 909.00 { 108 I 410 ~ 4,755
{ Beltli~e Road { 909.30 { { { (2)
] !'~e ~__t t" ........ l ........... 1 ............ i ........... 1 .........
{ St. Louis & : 910.30 i 108 [ 1,680 i 12,158
~ Soutbwes tern : 910.60
J_Rail~a~ ....... ~ ......... I .......... i ........... 1 ........
(1) Flow Area based on fully developed 100-year discharge, 55,800 cfs.
(2) Road is overtopped.
overtopped the road occurred in November 1981. This flood has been es-
timated to be apprcximately a 25-year flood. Beltline Road improvements
should avoid flooding of the roadway from the 100 year flood amd should have
no sdverse affect on upstream properties with regard to flooding.
F. ~xis ~i~g_~ili~a
Several utilities are in place within the existing Be~tline Road
right-of-way. ~he following are included:
1) a Lone Star Gas Pipelime,
2) an Americam Petrofina Pipeline,
3} an Explorer (Dorchester) Pipeline,
4) a 12-inch Sanitary Sewer Line,
5) a ~exas Power and Light Company overhead electric line, and
6) a City of Carroilton 12" water line.
Beltline Road is a major ~horou~hfare witbi~ the Citl of Coppell and
the City of Carrollton. ~he ultimate crcss-sectio~ for ~eltline Roed is a
6-l&ne divided thornughfare. ~s stated previcusl¥, MacArthur BouleYard and
Luna Road will cross ~eltline Road in the f~ture. ?hess roadways are also
projected to be 6-lane di~i~ed thoroughfares. ~he projected tr~£fic counts
fer these roadways are shown on ~igure 11. Projected traffic counts indic-
ate that Luna Road and ~acArthur Blvd. will each handle almost as much
~r~ffic as Beltline Road. ~be projected traffic volt.es show that proper
~esigs of these two road i~tersectio~s is e~tre~el~ important. I~pr~vements
to Beltline Road should not preclude either one of the other roads from
being properly imprcved.
Beltline Road crosses the Elm Fork of the Trinity River. The U.S.
Ar~;y Corps of Engineers has determined that the Elm Fork is a major waterway
within the United States. Therefore, the Corps of Engineers will review any
project that is to be constructed within the Elm Fork Floodplain to confirm
that there are no negative £mpact~ to the hydrology, hydraulics, or environ-
ment along the river. In addition, the Irving Flood Control District,
Section II! and the Farmers Branch Carrollton Flood Control District have
rec!ai~ed portions of the flood plain of the Elm Fork of the Trinity River
South of Belrliz:e Road. The ~orthwest Dallas County Flood Control District
lies tc the north of the Railroad and west of the river and is currently
reclaiming flood plain land. These agencies must also confirm that the
Beltline Road improvements will not adversely affect their reclamation
projects. The Federal Emergency Management Agency must review and approve
the project to confirm that the proposed improvements do not adversely
affect any property adjacent to, or upstream of the project, wirb regard to
flooding.
In addition to these agencies, the proposed imprcvememts must be
reviewed and approved by the Cities of Coppell, Irving, and Dallas; and
Dallas County, to assure compliance with all applicable standards and
speclficaticns.
DESIGN CRITERIA
III. DESIGN CRI%ERIA
~he City of Carrollton's Master Thoroughfare Plan has established
Beltline Road as a 6-lane divided minor arterial roadway (M6D). The City of
Carrollton's Standard design criteria for this type of roadway is included
in Appendix 1. %he Carrollton Standard allows tbe improved Beltlinm Road to
be constructed within a 100-foot wide right-of-way. The roadway will be
designed based on the full 6-lane cross-section with the initial phase of
construction being a 4-!ane roadway with a widened median. When traffic
counts reach a point where additional lanes are required, Beltline Road can
be widemed toward the median tc its ultimate cross-section. The recommep~ed
typical sections for the imitial and final construction plans are shown on
Figure 3.
The City of Carroilton Standard design spee~ for z six-lane divided
arterial is 45 mph. This design speed appears reasonable based on its use
for similar facilities of this type in the Dallas area and on tha 1984
"Policy on Geometric Design of Highways and Streets" published by the
American Society of State Highway and Transportation Officials (A~S~TO). It
is recommended that a design speed of 45 mph be adopted for tbe improved
Beltline Road.
Three items must be considered with regard to the design speed to
assure a safe, smooth riding roadway. %hese include vertical alignment,
horizontal alignment and stopping sight distance. The criteria established
by the City of Garrollton and AASH~O for these parameters have been reviewed
and are summarized in Table 2 belcw. In addition, City of Dallas criteria
are shown for comparison purposes. Consultation with Mr. Ed Powell,
Coppell's City Engineer, indicated that Coppell's standards are not let
written although an amalysis o~ the plans for MacArthur Boulevard morth o~
Beltline Road suggests that the Coppell standards may be lower than those
used by the cther agencies. AASHTO design criteria are based on ongoing
transportation research and are used as baseline data for the criteria of
other agencies. It is recommemded that the AASHTO standards be adopted for
Beltline Road.
l0
TABLE 2
STANDARD ROADWAY DESIGN CRIIERIA
[ ] Minimum ] Mi~i=uu ] Minixum ~
[ [K* Factor ~ Horizontal ~ Horizontal IMinim~
~ Maximum ~Crest/Sag I Curve :Curve l/4"/Foot ;Stoppingl
~ Grade ! ~ W/O Super I W/Super : Sight
.[___~a:~___i ....... i ......... l_~lc~i~___!__~!c~a~i~ .... i~i~an~ci
Carrollton 6% 84/85 840 -- ] 400
City of
Dallas 6% 69/44 1080 -- 310
AAS[{~0 6% 120/~ { ± 9000 845 400
City of ]
Coppell** -- 42/? I 850 -- 2~
K-L~, where L Length o~ vertical curve in feet
A = Algebraic difference of intersecting grades in percent.
**Based on MacArthur Boulevard plans north of Beltline Road.
1!
A large portion of the property with Beltline Road frontage from just
west of MacArthur Boulevard in Coppell to Hutton Branch in Carrolitoa has
been reclaim.ed from the Elm Fork flood plain by filling. In general, these
areas have been filled to a level of approximately two feet above the 100-
year fully developed water surface elevation. Because of the flat adjacent
land, Beltline Road will need to be constructed on a relatively flat
surface. The design will utilize minimum grades and a sequemce of alter-
nating crests and sags to create adequate drainage of the street. For the
at-grade segment it is recommended that the minimum sag elevation be set at
the 100-year fully developed flood water surface elevation and the maximum
crest elevation be set at the 100-year flood water surface elevation plus
one foot. Ihis will allow the areas immediately adjacent to the roadway to
drain to Beltline Road while still allowing the roadway to be at or above
the 100-year fully developed water surface.
At bridge lccations, it is recommended that the lcw chord of the
bridge beams be set a minimum of 2-feet aoove the 100-year fully developed
water surface. This will allow the 100-year flood to pass belcw the bridge
structure without significant head loss and will provide adequate freeboard
as a safety factor against floating debris and floods of greater magnitude.
12
ALTERNATIVE ALIGNMENTS
ALTerNAtIVE ALIGN[~NTS
If Beltline Road ks improved along the existing alignment, the
proposed improvements can not be accomplished within the existing right-of-
way at the ma~or street intersections. At these intersections, Beltline
Road amd the north-sooth intersecting streets must be raised to meet the
grade of the adjacent S.L.&S.W.R.R. This imcrease in elevation will cause
embankment slopes to extend beyond the available right-of-way and purchase
of either slope easements or additional right-of-way will be required. A
secondary impact of the raising of Beltline Road at these locations restrict
access to the properties adjacent to the imtersections.
Alternative solutions to the lack of the right-of-way at major
intersections include use of retaining walls adjacent to the roadways or
lowering the railroad rather than raising the streets and purchase of mddi-
tional right-of-way. Retaiming walls may prove economical at some
locations. However, lowering the railroad grade is considered to be too
expensive and time consuming and has not been further analyzed.
Additionally, over the entire length of the project, wherever
the Beltline Road embankment extends into the adjacent railroad right-of-
way, slope easements will be required and e~isting railroad drainage
facilities may need to be reconstructed. Other minor acquisitions of right-
of-wal or slope easements will be required at locations where the existing
13
right-of-way is less than 100 feet wide and at tlutton Drive where the inter-
section will have to be raised to meet flood criteria.
2.
As previously discussed, Beltline Road should be raised above
the fully developed 100-year flood water surface elevation of the Elm Fork
of the Trinity River add Hutton Branch. To accomplish this, Beltline Road
must be raised from 2 to 9 feet. Approximately 300,000 C.Y. of borrow
material will be required. At an estimated cost of $4.00/C.Y., the
timated fill cost is $1,200,000.
Two ma~or ~ngersectioms, MacArtbur Boulevard amd Luna Road, botk
6-lane major ghoroughfares are included in the easterly portion of the
[~roposed Beltline Road Improvements. If Beltline Road is ~mproved in its
present location, it must be raised at the Luna Road amd MacArthur Blvd.
ingersection, so thai crossing of ~he S.L. & S.W.R.R. can be accomplished.
In order to cross MacArthur and Luna, Beltline Road must be raised ap-
proximately 5 to 7 feet higher than what would be required to ,~eet 100 year
flood criteria. Luna Road will have to be reconstructed for approximately
525 feet sou~h of Beltline Road. Furthermore, a Lone Star Gas Company
metering station is located in~:ediately East of the Luna Road intersection.
This raising of Beltline Road will require either a relocation of the meter-
ing station or construcgion of retaining walls to protect the station. The
14
estimated cost fcr retaining walls at this location is ~50,000. If retain-
ing walls are constructed, access must be provided from Luna Road to the
metering station.
Construction plans for tbs proposed MacArthur Blvd. crossing of
the railroad have bean prepared by tbs firm, Nathan D. Maier Associates
(~DMA) on behalf of a landowner north of the railroad. The segment of these
plans at the railroad is shown on Figure 4. The ~DMA plans show MacArthur
Boulevard with a crest over the railroad tracks. The crest vertical curve
proposed gives a stopping sight distance on MacArthur Boulevard of only 280
feet. This distmnce is below the AASHTO recommendations and corresponds to
a design speed of approximately 35 mpb, which is 10 mph below the desired
design speed. Signalization of the Beltline-~acArthur intersection only
provides for control of traffic movements and will not ~ake the intersection
safer with regard to the stopping sight distance. Bringing the intersection
tc standard will require raising of MacArthur Boulevard for a longer dis-
tance north and south of Bel~line Road than is shown on the 5DMA plans.
If the Luna Road and MacArthur Blvd. intersections occur at the
present location on Beltline Road, the left turn lanes on both streets will
lie in the S.L. & S.~.R.R. railroad crossings. From a safety standpoints
this is a very undesirable condition because vehicles will be stopped on the
railroad crossing for extended periods of time during normal ~raffic
movements. Secondly, the intersection configuratien may have a detris;ental
effect on Beltline Road traffic because vehicles turning north from Beltline
to MacArthur will be backed up onto Beltline Road during train operations
(there will be no room to store vehicles on HacArthur Blvd. between Beltline
15
and the railroad gates). To offset this effect, the right (westbound to
northbound) and left (eastbound to northbouod) storage lanes would have to
be long enough to store sufficient ve~icles without affecting the through
Beltline traffic.
PuCton Drive will also require some minor improvements when
Beltline Road is improved. The Hutton Drive improvements will require
raising the roadway to meet the proposed Beltline Road grades.
Bridges across the Elm Fork of the ~rinity River and Hu£ton
Branch are signifi~ane concerms because the length of these bridges will
greatly impa¢: the total cost of the pro0ect. Table I lists the length of
the existing bridges in this reach of the river. The hydraulic effect of
the bridges on Beltline Road has been modeled with the U.S. Arn~ Corps of
Engimeer's Computer Model F~C-2 using a single model and a tri~le split flow
analysis. T~e model shows that all cf the existing bridge structures,
except the main channel bridge, are belcw the 100-year water surface eleva-
tion and must be removed and replaceC with the new structures regardless of
the alignment of Beltline Road. ~he main channel bridge has only 0.5 feet
of freeboard above the 1C0-year water surface, and it lies in the center of
the existing right-of-way. ~herefore, this bridge must also be removed and
replaced tc provide adequate freeboard to match the full roadway section
alignment.
~he center[ine of ~eltline Read is approximately 100 feet
downstream of the centerline of the S.L.&S.W. Railroad. Therefore, to
16
provide efficient flow ckrough the railroad and roadway bridge, the lengtk
of bridges on the proposed improved Beltline Road should approximately equal
the length of the existing railroad bridges. This assumption was made amd
tested with the t~C-2 model. It was found that this is a reasonable assump-
tion at each crossing, with the exception of the overflow bridge on tke west
side of the Elm Fork main channel. The existing railroad bridge at this
location is 1000 feet long, but it carries only apprnxi~mtely IG percent of
the total 100-year flow in the Elm Fork. The development north of the
railroad and west of the bridge has encroached +_250 feet on the west side of
the bridge, thereby reducirg its effective length to ?~0 feet. It was fnund
tkat the proposed Beltline Road bridge at this location length could be
reduced to 600-feet long by funneling the water into a smaller opening and
improvin~ the ckannel sownstream cf Beltline Road. This reduction will
retain the present flow distribution between the main channel and tke two
overflow bridges. Thus, the bridges required on the Elm For~ for ge[tlire
Road in its present lecatien irclude a 600-foot long ~ridge at the overflow
bridge west of the main channel, a 260-foot bridge on cee main channel, and
a 400-foot bridge on the overflow bridge east of the main channel for a
total length of 1,260 feet. Figure 5 shows a preliminary profile at each of
tke proposed bridges.
The hydraulic effects of these bridges are summarized in Tab~es
3 and 4 belcw:
l?
TABLE OF WATER SURFACE
DALLAS CO:J~ITY
EL~ FO~K HYDRAULICS SINGLE MODEL ANAL~SiS
JANUARY
: FENA MO~EL PROPOSE5
LOCATION ~STATiON FEMA MODEL UFSATE~ ~ELTL2ME PROPOSED
E:~ISTiH5 AT IMPROVE.
FILL EXISTIHG AT SOUTH.
PROJECTS LOCATIO~ ROUTE
(ELMBLTR) CBELTS~ (BELT4) CBELT~>
~EO.CO 459.~ 459.88 457.~ 459.91
8~5.~C q40.11 440.i0 440.10 440.00
701.55 - - 440.17 440.01
~.'S PFC? S~ ~02.~5 - 440.1~ 440.00
U/S P~CF ~R ~05.45 - 44C.2! 440.06
~95.30 ~40.24 440.2C 440.20 440.21
~O~.CO 440.18 440.15 440.15 45~.~4
~08.70 -
D.'S E"IST CR~ ~0~.50 45~.25 45~.27
: ~0~.5C 442° 10 442.07 441.?0 441.53
~ D!J.O0 442.4~ 442.45 442.24 441.5B
D/S ~AILFOAD: ~i3.JO 442.4~ 442.48 442.27 44i.~1
U/~ RAILROAD: ~!0.5J 442.55 442.~2 44~.5! 441.~
: 9ii.50 442.85 442.8~ ~42.~7 442.~5
: ~2G.~7 445.~ 445.90 445.75 44~.54
! ~5J.97 444.58 444.60 -
~SEL REFLECT IO0-YEAR FLOOD WITH FULLY DEVELOPED CONDITIONS~ 0=55800 CFS
!8
TgOLE 3F OATER SURFACE ELEVATIONS
:ALLAS C5URTY
ELR FORK HYSRAU..~ - SPLIT r.~g ~qALYSIS
3ANUARY 19S6
: I~ EXIOTIR6 CONDITION NOUEL ,." P£OFOSEU C~NDZTIGN NOCEL 11 PROPOSED CONOITION NOOEL
LOCATION :STATZON .," :I EX~STiNU AL:GNRENT ,," 3CUTHERR ROUTE .,"
~l LE?T C~ANREL I RZGHT .," LEFT CHANNEL RIGHT ~." LEFT : CNANREL RI6HT ,."
:l ~VER~ANg .'O~ER3ANK l; OVERSHNR - OVER3ANK ,," OVERSANR ; OVER3AN~ ,."
,, !SELT~L! :3ELT~C I (~ELTZR] ,,"(SELT4L! iBELT4C) (SELT4R) ,," iDELTPLI : (3ELT~C) (EELTPR! ,,"
.'~78.~0 .," 4~?,$~ 4~9.85 I 439.85 ,." 439.35 4~9.~5 4~9.$~ .," 437.G5 : 439.S5 439,80
I H95.9~ .." 440. Z& 440.2~ ' 440.!1 .." 440.26 440,19 440.!! .." 440.0~ ~ 44~.0! 440.02,,"
~/5 PROP ER : ~02.~5 'l I; .." 44~.07 : 440.05 439.E7 "
UfO PROP £~ I ~0~.45 :l ~: .~" 440.09 : 440.12 439.98 ,,"
; ~03,4~ I ..... ,, ,, 440.!0 I 440.!~ 440.02 ,,"
I ~5. Z~ :: 440.~0 440.~4 440.!3 ~ 440.~5 440.42 440.:4 I: 440.15 : 440.2? 4a0.33 :l
· .o. 0 440.~7 441.35 II
.' ~09.aG :: :43.:~ ~40.09 442.~C.." 4~2.4] 440.~ 442.96 ,," 442.:? ] A40,:6 442.4: 1:
. : n ~3 ': ~43.~0 441.C0 4~2.90 ~I ~42.49 ~41.35 443.20" 442.24 ] 440.:0 442.51 I:
315 EAILg:Gg~ 71:.30 :: 443.29 441.]0 443.G3.," 442.89 ~....9"4~ · 443.24,," 443.3! I 44Q.4G 442.50 .."
UI~ PA:L~CAO: 9!0.~0 :: 4~3.20 441.I0 443.0~ I: 442.96 441,4~ 44~.25 I: 442.33 ; 440.40 4~2.57 :I
As shown in the Tables, the water surface upstream of the rail-
road was lowered approximately 0.2 feet by the proposed bridge improvememts.
Computer output, water surface profiles, cross sections, and cross-eection
locations for this model are included in Appendix 2.
The Hutton Branch crossing will require a bridge approximately
260-feet long, giving a total length of bridge opening for the project of
1,520 feet. The total estimated cost of these bridges is $3,600,000.
5 · ~il i~ifla
As previously stated, there are several utilities which lie
along the existing Beltline Road right-of-way. These include:
1) a Lone Star Gas Pipeline,
2) an American Petrofima Pipeline,
3) an Ex~icrer (Dorchester) Pipeline,
4) a 12-inch Sanita~' Sewer Line,
5) a Texas Power and Light Company overhead electric line, and
6) a City of Carrolltom 12" water line.
The exact location of these utilities has not yet been determined, however,
approvals must be acquired from each utility company prior to construction.
In addition, provisions must be made so that these utilities are not damaged
during construction. Since fill will be placed on top of the existing
utility lines, they must be checked to assure that additional overburden
will not damage these lines.
2O
Fill will be placed under the existing Iexas Power and Light
Company overhead power line. Ibis line may have to be raised tc maintain
proper vertical clearance.
6.
As shown on Figure 2, there are four existing access points for
property owners north of the S.L.&S.W.R.R. gacb of these access roads cross
under the existing railroad bridge. If existing Beltlina Road is raised 2
re 9 feet to meet flood criteria, the vertical drop from the new roadway to
the area under the bridges would be increased significantly. The access
roads would have cc be reconstructed parallel to Bel~line Road, for some
distance withim railroad right-of-way to allow an adequate grade between
Belrline Road elevation and the elevation beicw each bridge. Access roads
parallel to Beltline Road would be an undesirable and unsafe condition.
an alternative, the access roads could be realigned so that they intersect
Beltlime Road at right angles and cross the S.L.&S.W.R.R. at grade. This
alternative may be more costly; but it would provide a more acceptable
design fcr private access.
Figure 12 shows that access to the north is limited along
Beltline Road since a crossing of the railroad would be needed. In addi-
tion, Figure 12 shows that visibility of the property north of Beltline is
blccked by the railroad embankment.
Beltline Road is a heavily traveled thoroughfare and an impor-
tant link to :brough traffic. It must therefore remain open at all times
during construction. This will require detouring traffic during
21
constructicn. The first phase of construction will require utility adjust-
merits including raising and relocating TP&L's overhead power line. In the
second phase of construction, the embankment, drainage system and pavement
for two eastbound lanes of Beltline Road will be constructed. In this
phase, only two of the tkree prcposed eastbound lanes at the bridges over
the main channel of the Elm Fork and Hutton Branch cam be constructed be-
cause of insufficient lateral clearance to tke existimg roadway. During
this time, traffic can remain on the existing roadway surface amd an in.-
proved shoulder on the north. (See Figure 6.) After the eastbound lanes of
the roadway and bridges are completed, traffic will be routed onto these
lanes. In the third phase of construction, the existing roadway will be
r~moved, and the embankment, drainage system and pavement for the westbound
lanes, including the westbound bridge lanes, will be constructed. In the
fourth and final ~hase of construction, the third eastbounC lane will be
constructed at the Elm Fork and Hutton Branch bridges.
At this time, the City of Carrollton is evaluating an option to
build six lanes of pavement in the roadway secticns of Beltline Road rather
than four lanes. If tbis option is chosen, three roadway lanes will be
built in Phase III instead of two. In Phase IV, the third lane of roadway
and bridges will be built on the scuth section after re-routing westbound
traffic onto tbe north lanes.
Traffic control will be a key activity during all p~ases of the
Beltline Road reconstruction because high speed traffic will be moving
imraediately adjacent to the construction area. Barrier rails and other
22
protective devices will have co be erected by the Contractor and construc-
tion equipment will be restricted from use of the existing roadway.
The estimated Contract time fcr construction of the project is
approximately 24 months exclusive of utility adjustments, which, depending
on the time of year could take between 3 and 4 months. This is based on
other Dallas County and City of Dallas Projects which were constructed under
similar traffic ccx~itlons. These projects are summarized i.m Table 5 belcw:
23
TABLE 5
CONSIRUCTION TIMING EXISIING ALIGNME~
{ [Approximate i Construction { Equivalent
Past i Length of { Contract Time !Construction
Hillcrest ]IH-635 ~o Spring Valley 1 mile 306 15
Greenville Ave. ~Royal Lane to IH-635 ~1.5 miles 235 12
Seagoville Road ~Acres to Picneer Road 2 miles 310
C~p Wisdom Road ~IH-355 to Houston School I mile 600 30
~ Road
Frankford Road ~East of Davenport to 1 mile 400 20
; Preston Road
*Abr~s Road ~Skillman t~ ;;almut m~ll i mile 60C 24
*Abr~:s Read was c~sed to ~raffic for approximately 12 months during construction.
24
Some of the listed projects do not include amy bridge construction.
Although construction of the bridges will occur simultaneously witb the
paving and drainage work, we estimate that the bridge portion of the projec~
will require 400 working days, although cee roadway portion could be tom-
ple[ed in 300 working days.
9.
The construction cost for tbe Beltline Road Improvements im the
present location have neen estimated and are shown in Table 6 below:
TABLE 6
ESII}~TED CONSTRUCTION COSTS
EXISTING ALIGNMENT
a. Sitework: $ 1,500,000
b. Paving: 1,52G,000
c. Drainage: 750,000
d. Bridges: ~.~L0J/.~Q
Total $ 7,370,000
Plus 15% Contingencies __1.~.~0
$ 8,500,000
These estimates are based on Unit Prices which have been estab-
lished by Dallas County Public Works and are based upon recent Dallas
County projects. The limits of the estimare are from tha west end of the
25
west Elm Fork overflow bridge to !H-35E. Detailed back-up for these cost
estimates are i~cluded in Appendix 3.
1.
Ihe proposed southern route for Beltline Road is shown in
Figure 7. To construct Beltline Road in this location, new right-of-way
must be acquired from each of the property owners along the route. On
~oven:ber 12~ 1985 a meetfng was held between representatives of Dallas
Coucty, the City of Coppeil's consulting engineer~ the City o~ Carrollton,
and property owners in Coppell and Carrollton to discuss gbe proposed
relccaticn. A list of the people that a~teeded this meeting is included in
Appendix 6. It was stated that if the proper~y owners woulc dedicate the
needed right-of-way for this alignmemt, then gke County woul~ release par-
cels of the existing right-of-way of ~eltline Road to compensate the
abutting property owner. This was agreed to conceptually by the affected
land owners at the meeting. However, each part}' stated tba~ mo firm commit-
ment could be made until the actual property descriptions were prepared and
the alignment was approved by both c~ty councils.
There is a portion of Beltline Road which crosses a lake owned by
the Fart, ers Branch-Carrollton Flood Control District. ~his lake is not used
for flood storage and, from an engineering standpoint, it could be filied~
ii a drainage culvert is constructed under Bel[line Road. ~he District has
stated no opposition to the Southern alignment, however mo firm commitment
will be made by the District until a formal request is submitted.
26
As discussed under section A.I, "Right-of-way Requirements"
Rutcon Drive must be r~ised at the Beltline intersection, if the road is
reconstructed along the existing alignment. This will require acquisition
of slope easements at the southeast and southwest corners of the Belt[ine
Road/Hutton Drive imtersection. The Southern Route will also require ac-
quisition of slope easements, as well as some additional right-of-way.
A portion of Eeltline Road west of MacArthur Boulevard to Moore
Road will be within Dallas Power & Light Company property. A copy of the
conceptual alignment has beem given to representatives of Dallas Power &
Light Company. No comme~:cs have been received as of this writimg.
Approxic.ately 80 percent of the area along the Southern Route has
been filled abcve ~he l~0-)'ear flood level by the Far, ers Branch-Carrollcon
Flood Control Distr~ct on the east, by Di~mnsion Development in thc mig~le
and by the Irving Flood Control District on the west. The areas recizinmd
by the flood control ~istr~cts were filled under the supervision of the
geotecbnical soil laboratories, Maxis. Engineers on c~e east, and Rone
Engineers on tke west. The fills were placed under densit} and moisture
control to 95 percent Standard Proctor Density at or above optimum n.oistore.
The existing f]lis are suitable fcr construction of roads. Letters from
Maxim Engineers and Rone Engineers are attached in Appendix 7, Iherefore,
very little borrow or erbankr:ent is required to construct Beltline Road
aicng tkis alignment. The only embankmen~ required to be constructed is at
the existing Farmers Branc~-Carrolito~ Flcod Control District lake and at
27
each bridge approach. Apprcximately 175,000 cubic yards of fill will be
required for this work. Approxi=ately 20,000 cubic yards of excavation will
be obtained from street excavation. Tbe additional 155,000 cubic yards can
be obtained from improvements to the existing Irving Flood Control District
Section Iii Elm Fork overflow swale and the Dimension Swale west of the Elm
Fork main channel. This is discussed in greater detail in Section 4.B.d,
Bridges and Drainage Structures.
Ihe Southern Route will greatly improve the Luna Road ~ntersec-
tion and =be Luna Road Crossing of the S.L.&S.W.R.R. If Beltline Road is
built ±§G0 ~ee= south of the existing alignment, it will allow Luna Road to
ri~e and safely cross the railroad at grade. Furthermore, thi~ revised
~!ignmen~ wii~ allow Luna Road to be ink,roved to overpass the rmiiroad if
ti;e Luna Road ann/or the railroae traffic increases to the degree ti~at a
grade separation becomes necessary. The profiles of these alternative
crossings are shown in Figure 8. Some slope easement~ will be required
along Luna Road to accomplish the railroad crossing at grade, but no slope
easemenZs are needed for Beltline Road.
This alternative will also require improvements to Luna Road.
Luna Road between Hutton Branch and Beltline Road is below the lO0-}ear
flood water surface elevation and was flooded in November 1981 by an es-
~i~:ated 25-year flood. It appears that the City of Garrollton shoule be
receptive to shar~ in tee cost of reconstructing Luna Road for two reasons.
2~
One, it will bring Luna Road above the IO0-year flood water surface eleva-
tion and two, it will allow Luma Road to safely cross the S.L.&S.~.R.R.
Hutton Drive will also require s~e improvements when Beltline Road is
raised. This improveu;en£ will require raising and revising the Hutton Drive
alig.-m:e~t at Beltline Road to provide a safe intersection. Again, this will
require the acquisition of slope easementa and/or additional right-of-way on
beth sides of existing Hutton Drive.
In the City of Coppeil, there are three street comnections to
Beltline Road, MacArtbur Boulevard, Mockingbird, and Moore Road. With the
Southern Route, the proposed MacArthur Boulevard crossing oi the railroad
can be made safer. The left turn lane on MacArtbur Boulevard will not be on
the railroad crossing. Also, the stopping sight distance on the crest at
the railroad crcssimg can be imcraased by adjusting the grades and increas-
ing the length of the vertical curve. This soutberm route will also allow a
grade separation at the railroad crnssimg if future traffic conditions
necessitated it.
At the MacArthur - Beltline Road intersection, the bridge rai-
lings et the gacArthur bridge over Grapevine Creek would cause a sight
obstruction only if a vehicle attempts to cross MacArthur with a red light.
The worst case stopping sight distance is 400 feet, which is withir the
AA~IITO standard.
Although the intersection will be only approximately 200 feet
north of the Grapevine Creek bridge, there is adequate room to provide a
t;imimum 200 feet of left turn storage. The MacArthur Boulevard median is
29
24 feet wide, which will allow the installation of two ll-fcot wide, 100-
foot long left turn lanes.
The Moore Road intersection can be accomplished without sig-
nificant problems if the S.L.&S.W.R.R. will approve a railroad crossing.
~he Mockingbird intersection can be accomplished without significant en-
gineering problems. The S.L.&S.W.R.R. must however grant approval for
another street crossing. An additional 200 foot long, 50-fnot wide bridge
must be constructed for Mockingbird to cross over Grapevine Creek. At $32
per square foot (based on Dallas County unit prices), the estimated cost for
the additional Crapevine Creek bridge is $320,000.
With tke proposed Southerm Route, Beltline Road will still cross
the Elm Fork of the Trinity River and Hutton Branch. The hydraulic effects
of Be!tline Road i~ this location have been evaluated with a simgle model
and a split flow analysis utilizing tke U. S. Army Corps of engineers com-
puter model HEC-2. The 100-year fully developed flcwrate of 55,800 cubic
feet ~er second was established as the design criteria to be met. The
detailed analysis has shown that with a total brid~e opening of 1260 linear
feet within the Elm Fork floodplai~ the water surface elevation upstream cf
the S.L.&S.W.R.R. is lowered approximately 0.6 feet. The results of this
analysis are shown in %abies 3 and 4. This table compares the water surface
in ~he left overbank, the channel, and the right overbar& for the existing
condition with eke water surfaces due tc the proposed Beltline Road
3O
improvements. Computer output, water surface profiles, cross sections, and
cross-section locations are included i~ Appendix 4.
The proposed Beltline Road southern alignment will require that
the existing Irving Flood Control Distr~ct Section Ill overflow swale be
extended upstrea~ of the proposed Beltline Road location. In addition, the
channel on tko east side of the main channel which was excavated for
reclamation of the property east of the main channel should also be extended
upstream of the proposed bridge. Approximately 155,000 cubic yards of
material will be generated from these improvements. This material will be
used to construct embankments at bridge approaches and to fill part of the
Farmers Branch-Carrollton Flood Control District lake as discussed in
Section 4.B.b, Embankment Requirements. To provide efficient flow, the
existing Beltline Road bridges will be removed. A schamatic plan view of
the proposed brJdse and channel improvements is shown in Figure 10.
The lengtk of the proposed Hutton Branch bridge is 360 linear
feet. As shown in Figure 10, this is an adequate length to completely cross
the existing channel without encroachment. The existing Hutton Branch
bridge will be removed once traffic is routed over the new bridge.
From MacArthur Boulevard in Coppell to Hutton Drive in
Carrollton, there are no existing utilities within the proposed alignment.
The only utilities near the Southern Route are a City of Copgell water line
and a sanitary sewer line which lie within the MacArthur Boulevard r~ght-of-
way amd a multiple duct under&round telephone conduit within the Luna Road
31
right-of-way. If the Southern Routa is selected, both the City of Coppell
and the City of Carrollton should be contacted to determine what utilities
these cities may wish to install along or across the street prior to
construction.
West of MacArthur Boulevard the southern route will cross an
existing Dallas Power & Light Company overhead electrical transmission line.
The southern route west of MacArthur will require close coordination with
and approval by Dallas Power & Light Company and the City of Dallas.
As previously stated there are four property owners north of the
~.L.&S.W.R.R. who presently gain access to their property from existing
~eltline Road. Ibis is shown in Figure 2. If Beltline Road is constructed
along the Southern Reute, access easememts should be provided from proposed
Beltline Road to these points. The two access poimts west of the Elm Fork
main channel and the access point at the East Elm Fork overflow bridge are
within the floodway of the Elm Fork o~ the Trinity River.
The feurth point of access lies approximately 350 feet east of
Luna Road. Access could be provided to this point f~om Luna Road along the
south right-of-way line of t~e S.L.&S.~.R.R. The acquisition of these
proposed access easements must be resolved tc relecate Beltline Road in the
Southern Route.
?. Cons
One of the major advantsges to using the southern al~gns;ent is
that it will allow all of Beltline Road, from Moore Road in Coppell to
32
Hutton Drive in Carrollton, to be constructed off-line without any traffic.
This means that all of the major bridges can be constructed without having
to contend with traffic and detouring.
Since the ~a~or portions of the Beltline improvemeots will be
constructed off-line, the ti~m for construction will be greatly reduced. We
estiu, ate that construction of the paving aod drainage for this project can
be completed in 180 wcrkimg days, or an equivalent total length of time of 9
months. This is based on similar paving and drainage projects which have
been recently completed. Some of these projects are summarized in Table
be!cw.
These projeccs did not include any bridge construction.
Construction cf the bridges could occur simultaneously with the paviEg and
dr&inage construction, however we do estimate that an additional 60 working
day, or 3 months, will be needed to complete the bridge work. Therefore,
the total estimated contract time to complete the Beltline Road imprcvememcs
is 220 working days for a total time of 12 months to complete the project.
33
TABLE ?
£ORSTRUCTION TIML~G
SOUiHER~ ROUTE
APPROXIFAIE CONSTRUCTION EQUiV,~EKT
LENGTH OF CONTRACT CONSIRUCTION
PAST PROJECT TIME PERIOD
MacArthur Irvin§ 4,500 140 C.D. 5
Freeport
Parkway Coppell 1,780 90 C.D. 3
Valwood
Park Famers Br. 11,100 155 W.D. 8
Fossil
Creek Fort Worth ?,000 150 8
34
9.
The estimated construction costs for the Beltline Road improve-
merits are Shown in Table 8 belcw:
TABLE 8
ESTIF~'~TED CO~STRDCTION COSTS
SOUTHERN ROUTE
Sitework $ 740,000
Paving 1,220,000
Draimage 636,000
Bridges
Subtotal $6,310,000
i~% Contingencies
Iotal $7,300,000
These estim:ates are based on unit prices from other comparable
projects which have been completed with no existing traffic or existing
utilities to deal wi~h. Limits for the estimate are from, tke west end of
the existing west Elm Fork cverflcw swale to iE-35£. Detailed back-up fcr
these cost estiuates are included in Appendix 5.
EVALUATION AND
RECOMMENDATIONS
V. EVALUAIION A~;D RECOM}:ENDATIONS
A. ~f~r~Y
l~provements tc Beltline Road in its existing alignment can be
rated as a safe adequate design when considering only Beltline Road.
However, when one also considers the Luna Road and the MacArtbur Boulevard
intersections with Beltline Rcad and the S.L.&S.W.R.R. crossings, the safety
of the existing alignment becomes questionable regarding stopping sight
distance and the traffic movements at railroad crossings. Moving these
intersections approximately 600 feet south of the railroad and eliminating
the need for vehicles to be stopped ir the left turn lanes and at traffic
signals on top of tko railroad is a definite safety advantage. The stopping
sight distance for the MacArtbur - Beltline intersection as it is designed
tcday is only 280 feet, which is below ~ke minimum AASHIC standard. The
minimum 400-foot stopping sight distance recommended by AASHTO can be
achieved by moving Beltline Road about 600 feet to the south.
The Froposed Southern Route utilizes reverse horizontal curves to
accomplish the rslocation of Beltline Road and these are aa safe as the
straight existimg alignment by designing these curves with radii and super-
elevetion which far exceed the City ef Carrollton, City of Dallas, and
AASHIO standards, this proposed alignment is as safe, if not safer than any
other major thoroughfare in tkis area.
Ihe greatest drainage consideration is the length of bridge re-
quired at the 51~ Fork and Hutton Branch. Our preliminary hydraulic
36
analysis indicates that with Beltline Road improved i~ the existing align-
ment, approximately 1,260 linear feet of bridge will be required at the Elm
Fork and 200 linear feet is needed to cross Hutton Branch. ~he total bridge
length needed will be about 1,460 linear feet. If Beltline Road is relo-
cated along the proposed Southern Route, the lengths nf bridge required will
be 1,260 linear feet at the Elm Fork and 380 limear feet at Hutton Branch
for a total of 1,640 linear feet of bridge.
If Mockingbird in the £ity of Coppell is to tie to Beltlime Road,
an additional bridge will be required to cross Grapevine Creek. ~he es-
timated cost of this bridge, based on Dallas County unit prices is $320,000.
As previously discussed, the estimated total time for construction
of the Belcline Road improvements in the existing right-of-way is 24 z,onths.
During this time traffic movement on Beltline Road, Luna Road, and MacArthur
~oulevard will be himderad due to construction and degonring. If Beltlioe
Road is built in the proposed Southern Route, the estimated total construc-
tion time is 12 months. Traffic movement will not be affected on Beltline
Road, MaeArtbur ~oulevard, nor on Luna Road since all construction will take
place off-line away from the existing roadways.
D. ~ost
The total cost fcr constructicn cf Beltline Read fro~ the west eod
of £be cverflow bridge west of the Elm Fork nain channel to 19-35£ are
summarized ic ~able 9.
37
TABLE 9
SUN}~RY Of ESTI}~TED COSTS
BOTH ALTERNATIVE ALIGNEENTS
Item Existing Alignment So~tb ! Cost
Sitewcrk $ 1,500,000 ~ 740,000 i <$ 760,000>
I
Paving I ,520,000 I ,220,000 ~ <300,000 >
I
Drainage 750,000 630,000 ~ <120,000>
i
[ Sub~otal $ 7,370,000 : $6,310,000 : <$1,060,000>
i~li~i~ ........ I~I~Q.Q~_ _i .... ~QQQ .... i ...... ~: .......
[ Total $ 8,500,000 , $7,300,000 ~ <S1,200,000>
38
As ahow~ in this table, the s{tework is leas costly for the
Southern Route. Thia is due to the fact that 60 ?ercent of the propoaed
route baa already beet filled and therefore very little borrow fur embank-
ments is required. The coat for paving and drainage is slightly leaa for
the Southern Route alan. Although tko total length of the roadway in-
creasea, there are more bridgea in the Southerr. Route so the actual amount
of paving and drainage decreasea. Also, the unit prices for the Southern
Route are less due to construction without traffic considerations. Since
there are more bridges in the Southern Route, the bridge cost for thia
alignment is greater than tbe bridge cost in the existing alignment.
As shown i~ the cost summary taole, the costs for bridges in the
Southern Route ia greater than the cost for bridges in the existing
alignment. However, this additional cost is off-set by the raduced cost
borrow material required and tke reduced cost of construction due to the
ability to construct the improvements off-line without traffic. In fact,
tkere ia still au est~:mted cost savings of $ 8~),000 wi:em tko cost of the
additional Mockingbird bridge over Grapevine Creek is considered. This
estimate was performed for tke section of Beltline Road from tko west end of
the overflew bridge west of the Elm Fork main channel to IH-35E. If a cost
analysis is performed for the section from tko west end of the overflow
bridge west of the Elm Fork to Moore Road in Coppell, an even greater cost
savings will be realized for construction in the Southern Route alignment
since again the roadway can be constructed without traffic.
We recommend tkat the Dallas County legal staff analyze in detail
all legal aspects of the alignments regarding right-of-way acquisitlcn,
39
access easement requirements, and legal ability to construct the roadway
along the proposed Southern Route instead of the existing alignment.
~. Reco~p~.~a~ig_R
Wi~en analyzing the two alternatives, ghe Southern Route is far superior
than the present alignment. The southern alignment will provide the safest.
most cost effective solution which can be constructed im the shortest time
frame. Therefore, from an engineering standpoint, we recommenC that Dallas
County pursue the realignment of Beltline Road along the proposed Southern
Rcute from Moore Road in Coppell to IH-35E in Carrollton.
4O
FIGURES
AREA OWNERSHE)
I J.B. WOOD
2 TRAMMELL CROW COMPANY
3 BETA PRODUCTS
4 W.L. GORDON COMPANY
5 F.B.C. - F.C.D.
6 BROSSEAU COMPANY
? THOMAS W. BLA_K. E JR.
8 D~MENSION
9 TRILAND/NORTHSTED JOINT VENTURE
- ' '~-~- ~ 10 TRILA N D/NORTHSTE-~I~/T VENTURE
11 DUNNING DEVELOPMENT
12 DUNNING DEVELOPMENT
13 CROW/BILMNGSLEY
14 DALLAS POWER & LIGHT CO.
........ STL- & sOUTHWESTERN RAILROAD--
,, I, ~ . '~: ... :.-~ .-. I ~ ~ .... ---,- ,. s
I! / ~ - .- -' ~' .. ~.''- ..... [. ~ .-..'-~ :-
/ / /~ , ~ ., ~ . {~) ........ ,. ,., ~ ....... . / -~---, l*-- -,[ ~
// i~.- ~ ~ v ' , Xx.~' ~" ......... ~ ~ .-- / L'~ ' :~ /~ 7 ~
/ . ~ , . - ........ _~. , ,
1~'~ _ , _ -., ,~--- ,-- ~:~ ... PROPERTY OWNERSHIP
/" : ; -~ .15 ~'~'~. ~'~ & ,'~/ BELT LINE ROAD
-- .................. ~ ~ Y T d~--- :~/~ '~.r.~ DA~S COU~ - PUBLIC WORKS DEPT.
.~' J I ~ SCALE I :2~ (A~ROX.) ~, 1986
TYPICAL SECTION
INITIAL CONSTRUCTION
t40T~/ DIM~N~IOIV~ SHC~VN
(N.T.S) ,,~E ~o ~c~
~_____o' ~. s' ~4' . I~' ~o'
I
FIGURE
, P--,'""''"" I ~'~ ~ PROPOSED ~ADWAY
~ i CROSS SECTIONS
BELT LINE ROAD
ALIGNME~ STUDY
~PICAL SECTION *~""~ "'"~"" ~ssoo~s,~.~.
FIN flL CONSTRUCTION
(N~S)
. . - ........ ~.~ ~ ',
:
.............. ~. ~ "-~
I
.. ........................... ., .......... ;..
__ ~'~'~ ~ ~ : ..... ~. .............. -: ......... ~ ~.-~ .... ~ ...... t ....... ~ ...... ~ .....
-: ::--_ .... · . -: - . _ . - } -- .: · ....::.~: . - ..- . ~..,~ .... . .... .
-.. ~ ' ._. ~ ' ' . . ' ' : .' .... ~ ~ -~ , ~ : ' ' I - - ~'~ ' ..... I~
....... ~ : ..... ~ : - - - ~ - - ~ -- ~- - - ~.~ ..... -'"}. i~ :
...., ~. ~.' - . ~ ~. . ~: ~ ~ ....... ~: -~ - · .q. - . ~: . , ~:~ ? ~:~
,~:"~ :~ ? ' ,~, ~. -' "~ t . :i~ . . ~1~ :... ,,e ........
I
H ~ ~';- ...... , --': .... '. --: ...... ~ ......... ' .... t ....... :'-" ~' "'~ ~ '~'r~' . - :.. .~!. . · ~'"'-":-"-~'-'~-~- ~ - - ' : ' - - ~- ......~ ;
. _ ............ !. . . . ,~, ~; : : z-'~ . -.. : ...... -.;[: . . . - : - :-,- · ..... ~ :- .... ~ - . , . -- -
: ............ ~ .... ~ ........ ... -...
................................... . . .:.," . . ,~:,. . ] - · ! - : .... ; .... .7%' - -:' L . - '.' - ' . . ' -' '. ........
i: - .! ~'~ '~' ' '': - '! ........
..................... ~ ~ - . . ,~.- i 7-z ;' . . ~ .
............... . ,. .~,~ ............. ~ .,;.~. , - · ..... ', ~ ~' z. . ..-~.. - ......
- _..~.~L ...................... ~,~ ..... ~ ............................... - ................
.... , ~ ~ - - I ; ....... ~--7- ..... '~- ..~ -;2~' -- .. ........
. . ~ - . . ~ ,~..~,~-~ ........ ~ · ~ , .. ~ .... - .............. [ - , . . . ~ · . .
' . ,'- - ..' ...... · ..... . - ~ - ,~"'~----~ ~ ' '-.,.- ' /' ' :~z'~ - : - : - :: ..... ' ' ~-"_ - [ . ' Z L- ' : .... :. ~ "' - - · . .
- · ......: ...... ~ ........... · t:' ! -l- ' t I' ' . . ,_- ..... ~ . :. . .... ~ ...... .t-. : ...... , .; .......
-': ~-t'-_z ZZ___- ' '' : _L~ __L_-_'~' :__-.LL_-.~:_' ' ' : .... !_~_" ' .:~.----__~.._: ..... - ....... -_;-- _. :_~:~_~Z_ ~_'__-'.-.l~ ...... ~ ............. ~- ~ ...... ,~ ........~ ................ ; ......... -'~ .................. z .....
- : ~ - - - : .......... . ..... . ' ~ i..- - --~ ...... ~] . ~ ~ . q l'. ~ ~ ' - , ~- . · '- - '-i~ .-: '.-, . - --: ..... ' - · '
.... ; ......... . ..... ~ ' - -' i.?-,, ' '~. ' ' ~.1 ' : '-'~:~ _: Z_ ~ f _- , ~., ' ;.' '~,! . ."7;.. ~ '~'iI~ · -~'[:' .... ~-.'l- ~1 . . ~, .. ' .....
..... ~ ~ ...... ~ "· ....... k~ ' ' ' ~' i:~ ¢-..' ' ''~i~ ~r,'_ '~'~-_. ~-'-.2._~___~_'-,. ..... t.__-~Z ~-~.._--' .......... ."Z_,.~._~Z~. ........,j,-- ~-~1~ ...... ~ .......... ~- ............... : ..................
'R~_.~"--Z'T-F' . : ...... ':-7%--7 .............. -'~' ~"~ '".~i~'--- ~_~. - -~1[ - --~;~ -- - ~.l? - i - ,"',.S ~ : ' · .~.* ' : - ~-~: ~i- - - ~.t*,' ' ",i~.- ~ ..... ~ ' ~l~' 4.' ' , '
. ; ..... ~ ~1.................. ·.... ...... ~ ........ . ~I= u ..... ..- _
,.--
ALLEYS 12
RES. 26
C2UA 36
C2UB 40
C4U 44
M4U 44
W4D 24 -24
M6D 33-33
P6D 36-36
NOTES : USE COLUWN I FOR ORDINARY TERRAIN HAVR~G AVERAGE GRADES FROM 0-8% . USE COLUI,ff~ 2 FOR ROLLING TERRAIN HAVING AVERAGE GRADES OVER 8%
THE MAXIhlUM PERCENT GRADE WITIDN 30 FEET OF A I,IAJOR THOROUGDFARE IS 3% . Tile
30 FEET OF THE INTERSECTION OF A RESIDENTIAL OR COLLECTOR STREET IS 5% .
A: THE ALGEBRAIC DIFFERENCE IN GRADES IN PERCENT. CARROLLTON , TEXAS
THOPOIJGHFARSS