Waterside E P2-CS 930722COPPELL PUBLIC WORKS
MEMORANDUM
DATE: July 22, 1993
TO: Larry Davis, Construction Inspector
FROM: ~ Howard L. Pafford, Utilities Superintendent
RE: Waterside Estates Phase II - Walk-through
Utilities personnel performed a walk through on the above referenced project this morning
and the following items need to be corrected prior to acceptance:
1. Paint fire hydrant valve caps red.
Paint proper letter on curbs stenciled or stamped, all letters (2) inches.
Manholes (MI-I) - Red paint
Mainline valve (MLV) - Blue paint
Fire Hydrant Valve (FHV) - Red paint
Meter Box (W) - Blue Paint
Sewer Cleanout (CO) - Red paint
Raise manhole to grade at Shorewood and Island Bay.
Lot 1 Block E - Water service leak
5. Lot 19 Block F - Replace LOt Clean out
6. Both irrigation services need proper -~" setters with dual checks.
All three blow offs need angle stops with close nipples and elbows pointed up.
All manholes need an approved rain pan.
9. Lot 21 Block F - Water service off at corporation stop.
Please ensure these items are corrected prior to final acceptance of the project.
HLP/dm