Waterside E P2-CS 920810 (2)COPPELL PUBLIC WORKS
DATE:
TO:
FROM:
RE:
August 10, 1992
Larry Davis, Construction Inspector l~/
Howard L. Pafford, Utilities Superintenden~
Walk-through Waterside Estates Phase II-A
The following water/sanitary sewer related items were found to be
deficient during this morning's walk through of the above
referenced project.
· ~Station 4 + 60.20 - Check bottom of manhole for
_ /~/ infiltration.
_1~.// Station 1 + 44.14 - Regrout (wipe) inside manhole ring.
3'/ Station 3 + 46.90 - Check invert for infiltration.
~/-'~ Station.4 + 28.34 - Regrout (wipe) inside manhole ring.
g. IrrigatIon Service between lots 37 & 38 Block F - Turn
lower curb stop up.
Please ensure that each of these items are corrected prior to
final acceptance of this project.
Thanks.
HLP/dm
WATRSIDE.HLP