ST9902-CS060104' Suzan Taylor - RE: W. Sandy Lake
Page 1 I
From:
To:
Date:
Subject:
"Brewer, Doug" <Doug. Brewer@atmosenergy.com>
"Suzan Taylor" <staylor@ci.coppell.tx.us>
1/4/2006 8:34:03 AM
RE: W. Sandy Lake
Suzan,
Driver Pipeline is our contractor on this project and they started
construction yesterday. We anticipate completion by the required date of
Jan. 9.
If you have any questions, feel free to write
Doug
..... Original Message .....
From: Suzan Taylor [mailto:staylor@ci.coppell.tx.us]
Sent: Tuesday, January 03, 2006 12:50 PM
To: Brewer, Doug
Subject: W. Sandy Lake
Doug:
I have been out of the office since December 22 and need to get an
update on the gas relocation on W. Sandy Lake. We were told that the
relocation would be complete by January 9th. Is that still a good date,
if not, when do you think the relocation will be complete?
Thanks
CC: "Hooker, Jeanne" <Jeanne. Hooker@atmosenergy.com>