ST9902-CS060117 (2)January 17, 2006
Louis Tiseo, Secreatry Treasurer
Tiseo Paving Company, Inc.
419 E. Hwy 80
Mesquite, TX 75105
RE: West Sandy Lake Road Project # ST 99-02A
NOTICE TO PROCEED WITH CONSTRUCTION
Dear Mr. Tiseo:
This letter will serve as your official notice to begin work on the referenced project. For
purposes of the contract, your calendar days will start January 30, 2006. Three hundred
(300) Calendar Days were bid on this project for completion of work. Therefore, if work
begins on January 30, 2006 then the calendar days on the project will expire on November
25, 2006.
If you have any questions or need any additional information please feel free to contact
Larry Davis, Construction Inspector at (972) 304-3685.
Sincerely,
Kenneth M. Griffin, P.E.
Director of Engineering & Public Works
Office 972/304-3686
Fax 972/304-7041
CC;
Suzan Taylor, CIP Coordinator
Larry Davis, Construction Inspector