Vista Point II 3-7-CS060124'January 24, 2006
COPPELL
Stacy Standridge
Standridge Companies
14860 Montfort Drive, #241
Dallas TX 75254
RE: Vista Point Il/Lots 3, 4, 5, 6 & 7, Block A
Final Acceptance Pending
Dear Mr. Standridge:
The attached letter was sent to Mr. Ken Newman of Scott & Reid General Contractors on
January 12, 2006. The purpose of the letter was to relay important information about items that
must be completed and/or supplied prior to acceptance of the infrastructure work by City of
Coppell Engineering Dept. I have had no response to the letter from anyone at Scott & Reid.
The items listed in the letter remain incomplete and acceptance is still pending as of this date. If
you have thc ability to influence the outcome of this close-out, please do what you can to move it
forward. Call me if you have any questions about final acceptance requirements or this letter.
Sin
Office Phone: (972) 304-3684
Fax: (972) 304-3570
CC:
Ken Newman, Scott & Reid General Contractors
Eric M. Hauglie, P.E., Pacheco Koch Consulting Engineers
Glenn Hollowell, P.E., Asst. Director of Public Works
Greg Jones, Chief Building Official
Tim Oates, Interim Fire Chief
COPPELL
January 12, 2006
Mr. Ken Newman, President
Scott 86 Reid General Contractors
15303 N Dallas Pkwy #150
Addison TX 75001
RE: Vista Point Il/Lots 3, 4, 5, 6 & 7, Block A
Final Acceptance Pending
Dear Mr. Newman:
Based on walk-thru inspections conducted in early December 2005, all punchlist items appear to
be complete except for general clean-up of the site, sidewalk completion and pavement repair on
Forest Hill Drive. There was some discussion of delaying the sidewalk until development of the
individual lots, but no final resolution has been reached.
It is apparent that your construction project has caused pavement damage in the street adjacent to
thc south properly line, on Forest Hill Drive. Please arrange to have the damage repaired to City
of Coppell standards as soon as possible. Also, please forward a copy of any final acceptance or
punchlist from City of Lewisville concerning work within their city relative to this project.
In addition, final acceptance of the project requires as-built plans From the engineer of record and
maintenance bonds for paving and utility installations. Please call me if you have any questions
about these requirements.
Sincerely.
Keith R. Marvin, P.E.
Assistant City Engineer
Office Phone: (972) 304-7044
Fax: (972) 304-3570
cc: David Solomon, City of Lewisville