Loading...
Anderson Addn-CS060125COFFELL January 25, 2006 Richard M. & Nina Rogers 421 Kaye Street Coppell, TX 75028 RE: Anderson Addition, Lots 31, 32 & 33 Fee Assessment Lettey Dear Mr. and Mrs. Rogers: Enclosed is a copy of the City of Coppell Development Fee Assessment table, along with a copy of the Development Fee calculations for the referenced development. Please make payment for the Roadway Impact Fee and Park Fee to the City of Coppell in the amount of $5,763.00 and forward to the Engineering Department along with a copy of the Fee Assessment table. This amount is a portion of the assessed fees that need to be paid prior to filing of the final plat. The collection of Water and Sewer Impact Fees is delayed until the issuance of the Building Permit. These fees are paid by separate check at the Building Inspections Department, located at 500 Southwestern Boulevard in the Fire Administration Building. Please note that fees associated with water and sewer services have only been assessed for the newly created lot. Should the required services to the new or existing lots be varied from the assessment, a reassessment may be required. Appropriate payment of the required fees will help insure a successful beginning of this project. We look forward to working with you on this project. If you have any questions, please contact me. Sincerely, Charlene La Matttna, E.I.T. Graduate Engineer cc: Jennifer Armstrong, Finance Director Mary Beth Spletzer, Administrative Secretary, Building Inspections Glenn Hollowell, Assistant Director of Public Works Greg Jones, Chief Building Official Brad Reid, Director of Parks and Recreation 25S PARKWAY 1~ PO.BOX 9478 1~ COPPELL TX 75019 ~ TEL 972/462 0022 ~c FAX 972/304 3673 DEVELOPMENT FEE TABLE Project: Anderson Addition, Lots 31, 32, 33 (Kaye Street) Date: 1/25/2006 TOTAL AMOUNT DUE FEES DUE PRIOR TO FILING PLAT Water Impact Fee $900.00 (100% due at Issuance of Building Permit) Water Tap Inspection Fee $50.00 (100% due at Issuance of Water Meter) Water Meter Fee (Domestic) $25.28 (100% due at Issuance of Water Meter) Water Meter Fee (Irrigation/Fireline) $0.00 (100% due at Issuance of Water Meter) Water Meter Deposit (Domestic) $30.00 (100% due at Issuance of Water Meter) lrrigation/Fireline Meter Deposit $0.00 (100% due at Issuance of Water Meter) Wastewater Impact Fee $900.00 (100% due at Issuance of Building Permit) Wastewater Tap Inspection Fee $50.00 (100% due at Issuance of Building Permit) Utility Final Inspection Fee $50.00 (100% due at Issuance of Building Permit) Park Fee $3,855.00 $3,855.00 (100% due prior to Filing Plat) Roadway Impact Fee $1,908.00 $1,908.00 (100% due prior to Filing Plat) Street Light Fee Information not Available (100% due prior to Acceptance of Project) II Street Sign Fee Information not Available (100% due prior to Acceptance of Project) II Construction Inspection Fee Information not Available (100% due prior to Start of Construction) II tOTAL $7,768.28 TOTAL AMOUNT DUE PRIOR TO FILING FINAL PLAT $5,763.00 DEVELOPMENT FEE WORKSHEET PROJECT: Anderson Addition, Lots 31, 32, 33 (Kaye StreeO DATE: 1/25/2006 Water Impact Fee: Domestic Meter(s): Irrigation Meter(s): Fireline Meter(s): 1 - 5/8 inch X 3/4 inch Total #: 1 ESU's @ $900.00 ea. (Due prior to issuance of building permit) Water Tap Inspection Fee: Total #: 1 Connections @ $5~00 ea. (Single family due prior to issuance of building permit) (All other developments due prior to issuance of meter) Domestic Water Meter Fee: Total #: 1 Domestic Meter(s) @ $25.28 (Single family due prior to issuance of building permit) (All other developments due prior to issuance of meter) Irrigation/Fireline Water Meter Fee: Total #: 0 Irrigation Meter(s) @ $0.00 Total #: 0 Additional Irrigation Meter(s) @ $0.00 Total #: 0 Fireline Meter(s) @ $0.00 (100% due prior to issuance of water meters) Domestic Water Meter Deposit Fee: Total #: 1 Meter(s) @ $30.00 ea. (100% due prior to issuance of water meters) Irrigation/Fire Meter Deposit Fee: Total #: 0 Meter(s) @ $30.00 ea. (100% due prior to issuance of water meters) Wastewater Impact Fee: Total Domestic Meters ESU's: 1 (Due prior to issuance of building permit) Wastewater Tap Inspection Fee: Total #: I Connections @ $50.00 ea. (100% due prior to issuance of building permit) @ $900.00 ea. Utility Final Inspection Fee (All developments): Total #: I Lots @ $50.00 ea. (100% due prior to issuance of building permit) 1 ESU's 0 ESU's 0 ESU's 0 ESU's $900.00 $50.00 $25.28 $0.00 $0.00 $0.00 $3O.OO $0.00 $900.00 $50.00 $50.00 Page 1 DEVELOPMENT FEE WORKSHEET Park Fee (For Residential Developments Only): * Preliminary plat approved: After October 26, 1993 Park Development Zone: 3 Single-family @ $1,285.00 per lot 0 Multi-family @ $1,285.00 per unit (100% paid prior to Council approval of final plat) Zone 1 $3,855.00 $0.00 $1,908.00 information not Available Roadway Impact Fee: (See attached fee calculations) Street Lighting Fees: Assessed for lighting in the City's right-of-way. This fee cannot be assessed until after T.U. Electric submits the lighting plan for the proposed development. Once the plans are submitted, $292.60 per light will be assessed. (100% due prior to final acceptance of development) Street Sign Fees: Assessed for signage in the City's right-of-way. (See attached fee calculations if applicable) Information not Available Construction Inspection Fees: A copy of the development contract must be submitted for assessment. The contracts should indicate the cost to construct the improvements that are inspected by the Engineering Depar[ment. (2% of development cost required for private improvements) (4% of development cost required for public improvements) Information not Available Page 2 ROADWAY IMPACT FEE CALCULATIONS PROJECT: DATE: Anderson Addition, Lots 31, 32, 33 (Kaye Street) 1/25/2006 ROADWAY IMPACT FEE: ,ervice Area * 1 ~ate~ory ** Residential Land Use ** Residential {Medium/Low) No. Lots/Units 3 Development Units ** 3.00 Vehicle Miles per Development Unit ** 4.24 Fee per Vehicle Mile *** $150 Roadway Impact Fee due = (Development Units) x _~- (Veh c e Miles per Development Unit) x (Fee per Vehicle Mile) = $1,908.00 * (Figure 4.1 - Roadway Impact Fee Study) ** (Table 4. I0 - Roadway impact Fee Study) *** (Schedule 2, Page 3 - The Master Fee Schedule)