ST9301-CS060118January 18, 2006
COFFELL
Doug Lovern, Right-of-way Agent
TXU
115 W. Seventh Street, Suite 725
Fort Worth, TX 76102
East Sandy Lake Road
Project # ST 93-01
Dear Mr. Lovem:
In 2002, we provided Sandy Lake Road plans to Jon Scarborough concerning the reconstruction of
East Sandy Lake Rd. On July 9, 2003, Mr. Scarbomugh responded back to the city that the
transmission lines across Sandy Lake Rd. would need to be raised 1 V2 foot or the road would need to
be lowered 1 V2 foot. In April 2003, the city finalized a contract with Jacobs Civil Inc. to redesign
Sandy Lake Rd. to lower the profile. Part of the scope was that Jacobs Civil Inc. would work
directly with Mr. Scaroborugh on the appropriate location and amount to lower the roadway.
In November 2003, Jacobs Civil Inc. provided revised plans to the City of Coppell and on
November 17, 2003 those plans were forwarded to Mr. Scarborough and copied to Brian Williams
and Shannon Gray showing that the road had been lowered to satisfy the clearance requirements for
the TXU transmission lines.
I hope this has adequately answered your concerns and if you should have any additional questions
please feel fi'ee to contact me.
Sincerely,
Kenneth M. Griffin, P.E.
Director of Engineering & Public Works