WA0101-CS060130COPPELL
January 30, 2006
Luis Velasquez
Fox Contractors, Inc.
PO Box 951
Midlothian TX 76065
RE: Project #WA 01-01 SH 121 Waterline Project, Coppell Rd to Denton Tap
Final Acceptance
Dear Mr. Velasquez:
The improvements in the above referenced project were inspected during construction by the City
of Coppell Engineering Department and were installed according to plans and our specifications
governing such work. The erosion control should be removed from the project limits upon receipt
of this letter.
As of today's date, the facilities are accepted subject to the two-year maintenance agreement.
Thank you for your cooperation during this construction, and if I can be of further service, please
contact me at (972) 304-3684.
Construction Inspector
Office Phone: (972) 304-3684
Fax: (972) 304-3570
Keith R. Marvin, P.E.
Assistant City Engineer
CCi
Ken Griffin, P.E., Director of Engineering & Public Works
Glenn Hollowell, P.E., Asst. Director of PuNic Works