ST9902-CS060203COPPELL MEMORANDUM TO: FROM: DATE: REF: Ken Griffin, City Engineer Keith Marvin, Asst. City Engineer Larry Davis, Construction Inspector February 3, 2006 ST 99-02 A, West Sandy Lake Rd - Work Activity Update Week of 1/30 to 2/3/06 1. Tiseo Paving has placed two project signs and two electronic information signs along with orange "Construction Zone" warning signs within the project area. 2. On Monday Jan. 30, Tiseo began preparations for installation of the erosion control for the project limits, but those preparations are not complete as of this date. 3. Verizon's overhead line switch from the poles marked for relocation appears to be complete. 4. TXU's activity at N Coppell Rd and W Sandy Lake adjacent to the Switching Station and Oakbend Addition is not complete at this time. They anticipate placement of the underground wire and switchgear sometime next week. This leaves vertical poles marked for relocation still standing from N Coppell Rd on Sandy Lake up to Freeport Pkwy. 1 feel the relocation won't be accomplished before mid-February. 5. 1 have had phone conversations and one personal meeting xvith Tiseo's project manager / superintendent. It appears that his xvork time is to be split between the two projects they have going concurrently in Coppell - East Sandy Lake Rd and West Sandy Lake Rd.