February 15, 2006
Mr. Larry Davis
Development Construction Inspector
City of Coppell
255 Parkway Boulevard
Coppell, Texas 75019
RE:
Landscape finalization along Plaza Boulevard
Coppell, Texas
DAA Job No. 03072C
Dear Larry:
The schedule to complete the landscaping irrigation and lighting is as follows:
1. Street light conduits and bases (28 lights)
2 to 3 weeks (finish March 6)
2. Sidewalks and Monumentation
2 to 3 weeks (finish March 31)
3. Install landscaping
2 to 3 weeks (finish April 21)
4. Install street Fights and cleanup
1 week (finish April 30)
The areas that we intend to improve are the common areas in the roundabout, the north-
south common area (east of Plaza Boulevard) and at the entry along SM ! 21.
We are waiting to install these improvements until the roadway infrastructure has been
finalized so that we do not conflict with this acceptance process. Hopefully the weather
will cooperate. If you have any questions, please contact me.