ST9902-CR06MART H E * C ] T Y * O F COPPELL MEMORANDUM TO: FROM: DATE: Ken Griffin, City En~ Keith Marvin~ ~ Larry Davis, ~ Inspector March 10, 2006 REF: ST 99-02 A, West Sandy Lake Rd - Work Activity Update Week of 3/6 to 3/10 1. The proposed change in grade and elevation of the 33" RCP from approximate STA 5+98 through STA 8+99 was received from Teague, Nail & Perkins and forwarded to Tiseo to alleviate the conflict with TXU's underground duct bank. 2. Contractor installed the fire hydrant at approximate STA 24+39. 3. Contractor began lowering the existing 12" water main at approximate STA 18+00 and approximate STA 15+60. 4. Contractor relocated and tested the fire hydrant at approximate STA 49+40. 5. Contractor cut and plugged the existing 10" water main at approximate STA 52+40. COl'FELL PROJECT PROJECT NO. OWNER UONTRACTOR PROJECT INSP W. SANDY LAKE ROAD {SH 121 to Coppell Rd N) ST 99-02 CITY of COPPELL TISEO PAVING LARRY DAVIS DAILY CONSTRUCTION REPORT /-~lT_lw IT IF IS IS I SI ~l~a~ (LEAR OVERCAST RAIN SNOV~ I AVERAGE FIELD FORCE NAME O~ C ON'I~ACTOR NON-MANUAL VISITORS REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: ,'-/' a // .', -- ' - /~ ' ' -; ' / /- f SIGNATURE PUBLIC WORKS INSPECTOR COl'F-ELL PROJECT PROJECT NO. OWNER CONTRACTOR PROJECTINSP W, SANDY LAKE ROAD (SH 121 to Coppell Rd N) ST 99-02 CITY of COPPELL TISEO PAVING LARRY DAVIS DAILY CONSTRUCTION REPORT AVERAGE FIELD FORCE NAMFE OF ( ONTRACTOR VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: SIGNATURE PUBLIC WORKS INSPECTOR COl'FELL PROJECT PROJECT NO. OWNER CONTRACTOR PROJECT INSP W. SANDY LAKE ROAD (SH 121 to Coppell Rd N) ST 99-02 CITY of COPPELL TISEO PAVING LARRY DAVIS DALLY CONSTRUCTION REPORT DATE '~ ' ~' ~ REPORT// ]M [LI~ /~F Is Is ~ AVERAGE FIELD FORCE NAME OF CONTRA{ TOR NON-MANI. JAL VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: SIGNATURE PUBLIC WORKS INSPECTOR COl'FELL PROJECT PROJECT NO. OWNER CONTRACTOR PROJECT INSP W. SANDY LAKE ROAD (SH 121 to Coppell Rd N) ST 99-02 CITY of COPPELL TISEO PAVING LARRY DAVIS DALLY CONSTRUCTION REPORT DATE~ '/~& REPORT// WEATIIER ] S[~ CLEAR OVERCAST RA~ r SNOW AVERAGE FIELD FORCE NAMt OF CON~]~A('TOR REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: SIGNATURE PUBLIC WORKS INSPECTOR COl'FELL PROJECT PROJECT NO. OWNER CONTRACTOR PROJECT INSP W. SANDY LAKE ROAD (SH 121 to Coppell Rd N) ST 99-02 CITY of COPPELL TISEO PAVING LARRY DAVIS DALLY CONSTRUCTION REPORT DATE 5 ' ?' ~C~ REPORT~ D,v In I~lw IT IF iS iSI WEATIIER SUN CLEAR OVERCAST RAIN [ SNOW AVERAGE FIELD FORCE NAME OF CONI'RACTOR VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT TIlE SITE: CONSTRUCTION ACTIVITIES: SIGNATURE PUBLIC WORKS INSPECTOR T H E · C I T Y . 0 F COl'FELL PROJECT PROJECT NO. OWNER CONTRACTOR PROJECTINSP W. SANDY LAKE ROAD (SH 121 to Coppell Rd N) ST 99-02 CITY of COPPELL TISEO PAVING LARRY DAVIS DALLY CONSTRUCTION REPORT REPORT# LM ITI~>ITIF Is rs i AVERAGE FIELD FORCE NAME OF CONTRACTOR VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: 7 SIGNATURE PUBLIC WORKS INSPECTOR COPPELL PROJECT PROJECT NO. OWNER CONTRACTOR PR~IECTINSP W. SANDY LAKE ROAD (SH 121 to Coppell Rd N) ST 99-02 CITY of COPPEEL TISEO PAVING LARRY DAVIS DAILY CONSTRUCTION REPORT "A'E A TItER SUN CLEAR OVERCAST RAFN [ SNOW AVERAGE FIELD FORCE N a. MIlE OF CON']I'RA ( TOR NON_MANUAL VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT TIlE SITE: CONSTRUCTION ACTIVITIES: SIGNATURE PUBI.IC WORKS INSPECTOR T H E . C I T Y . 0 F CoPPELL DAILY CONSTRUCTION REPORT PROJECT W. SANDY LAKE ROAD (SH 121 to Coppell Rd N) PROJECT NO. ST 99-02 OWNER CITY of COPPELL WEATIIER TEMP CONTRACTOR TISEO PAVING x,v I ND PROJECT INSP LARRY DAVIS DATE ~'~ ~/~'~:~ REPORT# IM ITIW ITI~.~S IS I AVERAGE FIELD FORCE NAME OF CON~fRACTOR VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: SIGNATURE PUBLIC WORKS INSPECTOR COP?-Ei3 PROJECT PROJECT NO. OWNER CONTRACTOR PROJECTINSP W. SANDY LAKE ROAD (SH 121 to Coppell Rd N) ST 99-02 CITY of COPPELL TISEO PAVING LARRy DAVIS DAILY CONSTRUCTION REPORT IL'~ITIw ITIrlsls I AVERAGE FIELD FORCE NAME OF CONYRACTOR NON-MANq3AL MANUAL REtvLaRKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: SIGNATURE PUBLIC WORKS INSPECTOR COPi:'ELL PROJECT PROJECT NO. OWNER CONTRACTOR PROJECT INSP W. SANDY LAKE ROAD (SH 121 to Coppell Rd N) ST 99-02 CITY of COPPELL TISEO PAVING LARRY DAVIS DAILY CONSTRUCTION REPORT AVERAGE FIELD FORCE NON-MANUAL MANUAL It. EMA~KS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: SIGNATURE PUBLIC WORKS INSPECTOR COPFELL PROJECT PROJECT NO. OWNER CONTRACTOR PROJECTINSP W. SANDY LAKE ROAD (SH 121 to Coppell Rd N) ST 99-02 CITY of COPPELL TISEO PAVING LARRY DAVIS DAILY CONSTRUCTION REPORT [M IT lC?IT IP IS IS I AVERAGE FIELD FORCE NON-MANUAL MANUAL REMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: _. . i ~ ...... -// · SIGNATURE PUBLIC WORKS INSPECTOR COPPELL PROJECT PROJECT NO. OWNER CONTRACTOR PROJECT INSP W. SANDY LAKE ROAD (SH 121 to Coppell Rd N) ST 99-02 CITY of COPPELL TISEO PAVING LARRY DAVIS DAILY CONSTRUCTION REPORT DATE '~ ~/~ ~ REPORT, IM IT Iw ItglF Is Is I AVERAGE FIELD FORCE N~ OF CONTRACTOR NON-MANUAL MANUAL P~VIARK$ VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: SIGNATURE PUBLIC WORKS INSPECTOR COFPELL PROJECT PROJECT NO. OWNER CONTRACTOR PROJECTINSP W. SANDY LAKE ROAD (SH 121 to Coppeli Rd N) ST 99-02 CITY of COPPELL TISEO PAVING LARRY DAVIS DALLY CONSTRUCTION REPORT DATE ~'~ ] 7' ~'~z~t~ REPORT # ]M ITtw IT 1~91s Is I AVERAGE FIELD FORCE NAbiE OF CONTRACTOR NON-MANUAL VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: :U % O%KS,NSPEUTOR COPPELL DAILY CONSTRUCTION REPORT PROJECT W. SANDY LAKE ROAD DATE ~ (SH 121 to Coppell Rd N) ~._/.~ REPORT # PROJECT NO. ST 99-02 o*Y OWNERCITY of COPPELL ~A~R ~ C~ O~CA~ ~ I S~OW CONTRACTOR TISEO PAVING ~mITyW~ PROJECT INSP LA~Y DAVIS S, VERAGE FIELD FORCE NAM]~ OF CONTRACTOR NON-MANUAL MANUAL REMAR]CS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: SIGNATURE PUBLIC WORKS INSPECTOR T H E ' C I T Y ' 0 F C-OP?ELL PROJECT PROJECT NO. OWNER CONTRACTOR PROJECT INSP W. SANDY LAKE ROAD (SH 121 to Coppell Rd N) ST 99-02 CITY of COPPELL TISEO PAVING LARRY DAVIS DAILY CONSTRUCTION REPORT DATE ~ ~ o~ }M I~lw IT IF Is Is I AVERAGE FIELD FORCE NAM~E OF CONTRACTOR NON-MANUAL VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: ~ .- .r ....... ~IuGB~I3 cT wURoERKs INSPECTOR COPi -EL[ DAILY CONSTRUCTION REPORT PROJECT W. SANDY LAKE ROAD DATE -~ '~ ~ REPORT # (SH 121 to Coppell Rd N) PROJECT NO. ST 99-02 DAY I M [ T I ~1 T } F I S I S I OWNER CITY of COPPELL W~ATHER ~ C~ O~CA~ ~ [ SNOW CONTRACTOR TISEO PAVING ~ITY w~ D~ S~I MM MM H~d High Rzpo~ No PROJECT INSP LA~Y DAVIS AVERAGE FIELD FORCE NAME OF CONTP. ACTOR NON-MANUAL MANUAl, / KEMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: SIGNATURE PUBLIC WORKS INSPECTOR COFFELL PROJECT PROJECT NO. OWNER CONTRACTOR PROJECTINSP W. SANDY LAKE ROAD (SH 121to CoppellRd N) ST ~-~ CITY ofCOPPELL TISEO PAVING LARRY DAVIS DAILY CONSTRUCTION REPORT DATE ~ - Z ~ -~ REPORT# DAY IM [T[W I~IF IS [S I ~ ~ o,~,,s~ ~ I s~ow NON-MANUAL MANUAL KEMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: Ae~ /~,.7 5;r ~I~.~ ..,~-, ,~r SIGNATURE PUBLIC WORKS INSPECTOR COFFELL DAILY CONSTRUCTION REPORT (SH 121 to Coppell Rd N) PROJECTNO. ST99-02 DAY I~ IT l w I x~s Is I OWNER CITY of COPPELL WEATHER SU~ CLEAR OVERCAST RAI~ I SNOW CONTRACTOR TISEO PAVING HUMIDIFyWEND Dry~ill MOdMod llishHulllidRegort NO PROJECT INSP LARRY DAVIS AVERAGE FIELD FORCE NON-MAN~AL MANUAL VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: T H E * C I T Y 0 r COPPELL PROJECT PROJECT NO. OWNER CONTRACTOR PROJECTINSP DAILY CONSTRUCTION REPORT W. SANDY LAKE ROAD DATE ~' ~2'~ REPORT' (SH 121 to Coppell Rd N) I~ ST99-02 1~^¥ IT IW IT IF IS [S ] CITY of COPPELL WEATHER SUN CLEAR O~RCAST RA~ I SNOW ~MP To 32 32-50 50-70 ~0~5 85 up TISEO PAVING HUM~ITyWIN~ D~StBi MoaM°d H~dHigh Repo~ NO LARRY DAVIS AVERAGE FIELD FORCE NAM~ OF CONTRACTOR NON-MA,~AL [ MANUAL REMARKS VISITORS TIME REPRESENTATIVE ;rEPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: - - '~', ; ' - ' · / - /', ' / SIGNATURE PUBLIC WORKS INSPECTOR T H E · C I T Y 0 F CO??ELL PROJECT PROJECT NO. OWNER CONTRACTOR PROJECTINSP W. SANDY LAKE ROAD (Slt 121 to Coppell Rd N) ST 99-02 CITY of COPPELL TISEO PAVING LARRY DAVIS DAILY CONSTRUCTION REPORT DAY IM ['~W IT IF Is Is ] AVERAGEFIELDFORCE NAME OF CONTRACTOR NON-MANI~AL MANUAL I REMARKS ~'ORi REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: SIGNATURE PUBLIC WORKS INSPECTOR COFFELL PROJECT PROJECT NO. OWNER CONTRACTOR PROJECT INSP W. SANDY LAKE ROAD (SH 121 to Coppell Rd N) ST 99-02 CITY of COPPELL TISEO PAVING LARRY DAVIS DALLY CONSTRUCTION REPORT ~,-~ o^¥ IM IT I~[T IF IS IS I AVERAGE FIELD FORCE NA~{E OF CONTRACTOR VISITORS TIME REPRESENTATIVE NON-MANUAL MANUAL REMARKS REPRESENTING REMARKS EQUIPMENT AT THE SITE: :ONSTRUCTION ACTIVITIES: SIGNATURE PUBLIC WORKS INSPECTOR COPPELL PROJECT PROJECT NO. OWNER CONTRACTOR PROJECT INSP W. SANDY LAKE ROAD (SH 121 to Coppell Rd N) ST 99-02 CITY of COPPELL TISEO PAVING LARRY DAVIS DAILY CONSTRUCTION REPORT DATE ~ ~ ff F~ REPORT # Im ]TIW IT~ISIs I WEATHER SUN CLEAR OVERCAST RAIN ] SNOW TEMP TO 32 32-50 50-70 70-85 85 up AVERAGEFIELD FORCE NAMIE OF CONTRACTOR NON-MAN"UAL MANUAL R3EMARKS VISITORS TIME REPRESENTATIVE REPRESENTING REMARKS EQUIPMENT AT THE SITE: CONSTRUCTION ACTIVITIES: ..... [/- - , SIGNATL~E PUBLIC WORKS INSPECTOR