Amberpoint BP 2R-CS051012T H E ¢ I T Y 0 F
COPPELL
October 12, 2005
Mark W. McGraw, P.E.
Halff Associates, Inc.
8616 Northwest Plaza
Dallas, TX 75225
RE: Aanberpoint Lot 2R, Block A
REVISED Fee Assessment Letter
Dear Mr. McGraw:
Enclosed is a revised copy of the City of Coppell Development Fee Assessment table, along with a copy
of the Development Fee calculations for the referenced development. On August 23, 2005, City Council
approved the award of the yearly bid for the purchase of water meters. This revised assessment reflects
the new meter prices.
No payment is due to the City of Coppell for Roadway impact fees due to the December 4, 2001
development agreement covering the entire Amberpoint Business Park. Water and Sewer Impact Fees are
not collected until the issuance of a Building Permit.
Please provide a copy of the Engineer's estimate or contract to our office so the 2% & 4% construction
inspection fee can be verified. The construction inspection fees must be paid prior to the scheduled pre-
construction meeting.
The additional fees for water and sewer taps, water meters, and utility inspection fees need to be paid by
separate check at the new Public Works Service Center, 816 S. Coppell Road. Meters will be ordered
when those fees are paid.
Appropriate payment of the required fees will help insure a successful beginning of this project. We look
forward to working with you on this project. If you have any questions, please contact me.
Sincerely,
Charlene La Mattin~ E.I.T.
Graduate Engineer
CC:
Jennifer Armstrong, Finance Director
M?~v Beth Spletzer, Administrative Secretary, Building Inspections
~i~nn Hollowell, Assistant Director of Public Works Greg Jones, Chief Building Official
DEVELOPMENT FEE TABLE
Project: Amberpoint Lot 2R, Block A
Date: 10/12/2005
TOTAL AMOUNT DUE
FEES DUE PRIOR TO
FILING
PLAT
Water Impact Fee $11,900.00
(100% due at Issuance of Building Permit)
Water Tap Inspection Fee $350.00
(100% due at lssuance of Water Meter)
Water Meter Fee (Domestic) $613.02
(100% due at Issuance of Water Meter)
Water Meter Fee (Irrigation/Fireline) $9,491.18
(100% due at Issuance of Water Meter)
Water Meter Deposit (Domestic) $90.00
(100% due at Issuance of Water Meter)
Irrigation/Fireline Meter Deposit $120.00
(100% due at Issuance of Water Meter)
Wastewater Impact Fee $6,720.00
(100% due at Issuance of Building Permit)
Wastewater Tap Inspection Fee $150.00
(100% due at Issuance of Building Permit)
Utility Final Inspection Fee $150.00
(100% due at Issuance of Building Permit)
Park Fee $0.00 $0.00
(100% due prior to Filing Plat)
Roadway Impact Fee $0.00 $0.00
(100% due prior to Filing Plat)
Street Light Fee Information not Available
(100% due prior to Acceptance of Project) II
Street Sign Fee Information not Available
(100% due prior to Acceptance of Project) l[
Construction Inspection Fee Information not Available
(i 00% due prior to Start of Construction)
TOTAL $29,584.20
TOTAL AMOUNT DUE PRIOR TO FILING FINAL PLAT $0.00
DEVELOPMENT FEE WORKSHEET
PROJECT: Amberpoint Lot 2R, Block A
DATE: 10/12/2005
Water Impact Fee:
Domestic Meter(s):
Irrigation Meter(s):
Fireline Meter(s):
3 - 2 inch = 24 ESU's
2 - 2 inch = 16 ESU's
0 = 0 ESU's
2 - 8 inch 2.5 ESU's
Total #: 42.5 ESU's @ $280.00 ea.
(Due prior to issuance of building permit)
Water Tap Inspection Fee:
Total #:
7 Connections @ $50.00 ea.
(Single family due prior to issuance of building permit)
(All other developments due prior to issuance of meter)
Domestic Water Meter Fee:
Total #: 3 Domestic Meter(s) @ $204.34
(Single family due prior to issuance of building permit)
(All other developments due prior to issuance of meter)
Irrigation/Fireline Water Meter Fee:
Total #: 2 Irrigation Meter(s) @ $204.34
Total #: 0 Additional Irrigation Meter(s) @ $0,00
Total #: 2 Fireline Meter(s) @ $4,541.25
(100% due prior to issuance of water meters)
Domestic Water Meter Deposit Fee:
Total #: 3 Meter(s) @ $30.00 ea.
(100% due prior to issuance of water meters)
Irrigation/Fire Meter Deposit Fee:
Total #: 4 Meter(s) @ $30,00 ea.
(100% due prior to issuance of water meters)
Wastewater Impact Fee:
Total Domestic Meters ESU's: 24
(Due prior to issuance of building permit)
$280.00 ea.
Wastewater Tap Inspection Fee:
Total #: 3 Connections @ $50.00 ea.
(100% due prior to issuance of building permit)
Utility Final Inspection Fee (All developments):
Total #: 3 Lots @ $50.00 ea.
(100% due prior to issuance of building permit)
$11,900.00
$350.00
$613.02
$408.68
$0.00
$9,082.50
$90.00
$120.00
$6,720.00
$150.00
$150.00
Park Fee (For Residential Developments Only):
Page 1
DEVELOPMENT FEE WORKSHEET
* Preliminary plat approved:
After October 26, 1993
Single-family @ $0.00 per lot
Multi-family @ $0.00 per unit
(100% paid prior to Council approval of final plat)
$0.00
$o.oo
$0.00
Information not Available
Roadway Impact Fee:
(See attached fee calculations)
Street Lighting Fees:
Assessed for lighting in the City's right-of-way.
This fee cannot be assessed until after T.U. Electric submits
the lighting plan for the proposed development.
Once the plans are submitted, $292.60 per light will be assessed.
(100% due prior to final acceptance of development)
Street Sign Fees:
Assessed for signage in the City's right-of-way.
(See attached fee calculations if applicable)
Information not Available
Construction Inspection Fees:
A copy of the development contract must be submitted for assessment.
The contracts should indicate the cost to construct the improvements
that are inspected by the Engineering Department.
(2% of development cost required for private improvements)
(4% of development cost required for public improvements)
Information not Available
Page 2
ROADWAY IMPACT FEE CALCULATIONS
PROJECT:
DATE:
Amberpoint Lot 2R, Block A
10/12/2005
ROADWAY IMPACT FEE:
Service Area * 4
Category ** Industrial
Land Use ** General Light Industrial
Building Area (sf) 713,918
Development Units ** 713.92
Vehicle Miles per Development Unit ** 1.06
Fee per Vehicle Mile *** $300
Roadway Impact Fee due = (Development Units) x
(Vehicle Miles per Development Unit) x (Fee per Vehicle Mile) = $227,025.92
* (Figure 2 - Roadway Impact Fee Study)
** (Table 3 - Roadway Impact Fee Study)
*** (Schedule 2, Page 3 - Roadway Impact Fee Study)
Percent of Credit Toward Roadway Impact Fees 100%
Total Credit $227,025.92