Amberpoint BP 2R-LR060303CONCRETE COMPRESSIVE STRENGTH TEST
Report Number: 94051418.0153
Service Date: February 2, 2006
'lrerracon
8901 Carpenter Frwy, Ste #100
Dallas, Texas 75247
(214) 630-1010
Client:
Transwestem Commercial Services
Attn: David Gunderson
5001 Spring Valley Rd Ste 600 W
Dallas TX 75244
Report Date: March 03, 2006
Project: AmberPoint Business Park
Buildings 4, 5 and 6
505 South Royal Lane
Coppell, TX
Project No.: 94051418
Material Information
Specified Strength: 4000 psi ~ 28 Days
Batch Time: 2:50pm
Supplier: Lattimore
Truck No: 964
Mix I.D. No.: 1851
Water Added Onsite Before Test:
Water Added Onsite After Test:
Field Test Data
Test Result
Slump, inches: 4.50
Air Content, %: 3.1
Concrete Temperaturep F: 84
Ambient Temperature,o F: 75
Plastic Unit Weight, pcf:
Laboratory Test Data
Set Specimen Diameter Area
No.
Plant: 3
Ticket No: 3208417
0Gallons
0 Gallons
ID (inches) (sq. inches)
Sample Information
Date Cast: February 2, 2006
Technician: Ira S. Haynes
Weather Conditions: Clear
Accumulative Yards: 9/9
Placement Method: Direct Dischapge
Sample Locations: Sra. 3+87.84, Line C
Placement Location: Inlet
Specification
Time: 4:05pm
Test Method
ASTM C143
ASTM C231
ASTM C1064
ASTM C1064
ASTM C138
Age at Maximum Compressive
Date Test Load Strength
Tested (days) (lbs) (psi)
1 1 6.00 28.27 02/09/2006 7 96,330 3,410
1 2 6.00 28.27 02/09/2006 7 96,580 3,420
Average (7 Days) 3,420
1 3 6.00 28.27 03/02/2006 28 142,280 5,030
1 4 6.00 28.27 03/02/2006 28 129,940 4,600
Average (28 Days) 4,820
Comments: Not tested for plastic unit weight.
Services - Obtain samples of fresh concrete at the placement locations, perform required field tests and cast compressive
strength samples.
Technician: Ira S. Haynes
Report Distribution:
Transwestern Commercial Services (1) O'Brien & Assoc ~' J.~j~/ ~ j
(1)
(1) City of Coppell TX (1) TechniStructures Reviewed by:
(1) City of Coppell TX Hussein H. Abusaad, P.E.
(1) Rogers O*Brien Construction Co Senior Project Manager
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable
to the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical
materials.
CONCRETE COMPRESSIVE STRENGTH TEST
· Report Number: 94051418.0154
Service Date: February 2, 2006
'lrefracon
8901 Carpenter Fr~vy, Ste #100
Dallas, Texas 75247
(214) 630-I010
Client:
Transwestern Commercial Services
Attn: David Gunderson
5001 Spring Valley Rd Ste 600 W
Dallas TX 75244
Report Date: March 03, 2006
Project: AmberPoint Business Park
Buildings 4, 5 and 6
505 South Royal Lane
Coppell, TX
Project No.: 94051418
Material Information
Specified Strength: 4600 psi @ 28 Days
Batch Time: 7:00am Plant: 2
Supplier: Potter Concrete
Truck No: 113 Ticket No: 102523
Mix I.D. No.: 7723
WaterAdded Onsite Before Test: 10Gallons
Water Added Onsite After Test: 0 Gallons
Sample Information
Date Cast: February 2, 2006 Time: 7:17am
Technician: Marlo A. Garcia
Weather Conditions: Cool, partly cloudy, cool bree
Accumulative Yards: 50/340
Placement Method: Direct Discharge
Sample Locations: See attached sketch for Location #1
Placement Location: Pavement, See attached sketch for location
poured
Field Test Data
Test
Result
Slump, inches: 6.25
Air Content, %: 5.2
Concrete Temperaturep F: 68
Ambient Temperature,o F: 56
Plastic Unit Weight, pcf:
Laboratory Test Data
Set Specimen Diameter Area
No. ID __ (inches) (sq. inches)
1 1 6.00 28.27
1 2 6.00 28.27
I 3 6.00 28.27
1 4 6.00 28.27
Specification
Test Method
3-5 ASTM C143
3-5 ASTM C231
ASTM C1064
ASTM C1064
ASTM C138
Age at Maximum Compressive
Date Test Load Strength
Tested (days) (lbs) (psi)
02/09/2006 7 99,600 3,520
02/09/2006 7 96,200 3,400
Average (7 Days) 3,460
03/02/2006 28 134,090 4,740
03/02/2006 28 130,460 4,610
Average (28 Days) 4,680
Comments: Not tested for plastic unit weight.
Services - Obtain samples of fresh concrete at the placement locations, perform required field tests and cast compressive
strength samples.
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not bo reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable
to the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical
materials.
CONCRETE COMPRESSIVE STRENGTH TEST
' Report Number: 94051418.0154
Service Date: February 2, 2006
6901 Carpenter Frwy, Ste #100
Dallas, Texas 75247
(214) 630-1010
Client:
Transwestern Commercial Services
Attn: David Gunderson
5001 Spring Valley Rd Ste 600 W
Dallas TX 75244
Report Date: March 03, 2006
Project: AmberPoint Business Park
Buildings 4, 5 and 6
505 South Royal Lane
Coppell, TX
Project No.: 94051418
Material Information
Specified Strength: 4600 psi ~ 28 Days
Batch Time: 8:10am Plant: 2
Supplier: Potter Concrete
Truck No: 122 Ticket No: 102536
Mix I.D. No.: 7723
WaterAdded Onsite Before Test: 10Gallons
Water Added Onsite After Test: 0 Gallons
Sample Information
Date Cast: February 2, 2006 Time: 8:28am
Technician: Marlo A. Garcia
Weather Conditions: Cool, sunny & mild breeze
Accumulative Yards: 180
Placement Method: Direct Discharge
Sample Locations: See attached sketch for Location #2
Placement Location: Pavement, See attached sketch for location
poured
Field Test Data
Test
Result
Slump, inches: 6.00
Air Content, %: 5.3
Concrete Temperature,o F: 68
Ambient Temperature,o F: 61
Plastic Unit Weight, pcf:
Laboratory Test Data
set Specimen Diameter Area
No. ID (inches) (sq. inches)
2 I 6.00 28.27
2 2 6.00 28.27
2 3 6.00 28.27
2 4 6.00 28.27
Specification
3-5
3-5
Test Method
ASTM C143
ASTM C231
ASTM C1064
ASTM C1064
ASTM C138
Age at Maximum Compressive
Date Test Load Stren~.th
Tested (days) (lbs) (psi)
02/09/2006 7 99,090 3,500
02/09/2006 7 106,150 3,750
Average (7 Days) 3,630
03/02/2006 28 98,540 3,480*
03/02/2006 28 134,270 4,750
Average (28 Days) 4,120
Comments:* Does not comply with specified strength. Not tested for plastic unit weight.
Services - Obtain samples of fresh concrete at the placement locations, perform required field tests and cast compressive
strength samples.
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the uae of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable
to the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical
materials.
CONCRETE COMPRESSIVE STRENGTH TEST
Report Number: 94051418.0154
Service Date: February 2, 2006
']rEffacon
8901 Carpenter Frwy, Ste #100
Dallas, Texas 75247
(214) 630-1010
Client:
Transwestern Commercial Services
Attn: David Gunderson
5001 Spring Valley Rd Ste 600 W
Dallas TX 75244
Report Date: March 03, 2006
Project: AmberPoint Business Park
Buildings 4, 5 and 6
505 South Royal Lane
Coppell, TX
Project No.: 94051418
Material Information
Specified Strength: 4600 psi ~ 28 Days
Batch Time: 9:22am Plant: 2
Supplier: Potter Concrete
Truck No: 107 Ticket No: 102547
Mix I.D. No.: 7723
Water Added Onsite Before Test: 10Gallons
Water Added Onsite After Test: 0 Gallons
Sample Information
Date Cast: February 2, 2006 Time: 9:40am
Technician: Mario A. Garcia
Weather Conditions: Cool, sunny & mild breeze
Accumulative Yards: 270
Placement Method: Direct Discharge
Sample Locations: See attached sketch for Location #3
Placement Location: Pavement, See attached sketch for location
poured
Field Test Data
Test
Result
Slump, inches: 6.00
Air Content, %: 5.5
Concrete Temperaturep F: 68
Ambient Temperature,o F: 66
Plastic Unit Weight, pcf:
Laboratory Test Data
Set Specimen Diameter Area
No. ID (inches) (sq. inches)
3 1 6.00 28.27
3 2 6.00 28.27
3 3 6.00 28.27
3 4 6.00 28.27
Specification
3-5
3-5
Test Method
ASTM C143
ASTM C231
ASTM C1064
ASTM C1064
ASTM C138
Age at Maximum Compressive
Date Test Load Strenc, th
Tested (days) (lbs) (ps~)
02/09/2006 7 115,900 4,100
02/09/2006 7 109,480 3,870
Average (7 Days) 3,990
03/02/2006 28 142,050 5,020
03/02/2006 28 143,210 5,060
Average (28 Days) 5,040
Comments: Not tested for plastic unit weight.
Services - Obtain samples of fresh concrete at the placement locations, perform required field tests and cast compressive
strength samples.
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable
to the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical
materials.
CONCRETE COMPRESSIVE STRENGTH TEST
Report Number: 94051418~0154
Service Date: February 2, 2006
'lrerracon
8901 Carpenter Frwy, Ste #100
Dallas, Texas 75247
(214) 630-1010
Client:
Transwestern Commercial Services
Attn: David Gunderson
5001 Spring Valley Rd Ste 600 W
Dallas TX 75244
Report Date: March 03, 2006
Project: AmberPoint Business Park
Buildings 4, 5 and 6
505 South Royal Lane
Coppell, TX
Project No.: 94051418
Material Information
Specified Strength: 4600 psi ~ 28 Days
Batch Time: 10:35am Plant: 2
Supplier: Potter Concrete
Truck No: 113 Ticket No: 102558
Mix I.D. No.: 7723
Water Added Onsite Before Test: 0Gallons
Water Added Onsite After Test: 5 Gallons
Sample Information
Date Cast: February 2, 2006 Time: 9:40am
Technician: Marlo A. Garcia
Weather Conditions: Cool, sunny w/cool breeze
Accumulative Yards: 370/410
Placement Method: Direct Discharge
Sample Locations: See attached sketch for Location #4
Placement Location: Pavement, See attached sketch for location
poured
Field Test Data
Test
Specification
3-5
3-5
Result
Slump, inches: 5.50
Air Content, %: 5.4
Concrete Temperaturep F: 71
Ambient Temperature,o F: 69
Plastic Unit Weight, pcf:
Laboratory Test Data
set Specimen Diameter Area
No. ID (inches) (sq. inches)
4 1 6.00 28.27 02/09/2006
4 2 6.00 28.27 02/09/2006
4 3 6.00 28.27 03/02/2006
4 4 6.00 28.27 03/02/2006
Date
Tested
Test Method
ASTM C143
ASTM C231
ASTM C1064
ASTM C1064
ASTM Cl 38
Age at Maximum Compressive
Test Load Strength
(days) (lbs) (psi)
7 113,400 4,010
7 110,150 3,900
Average (7 Days) 3,960
28 154,670 5,470
28 I50,840 5,330
Average (28 Days) 5,400
Comments: Not tested for plastic unit weight.
Services - Obtain samples of fresh concrete at the placement locations, perform required field tests and cast compressive
strength samples.
Technician: Marlo A. Gamia
Report Distribution: ~a
(1) Transweslern Commercial Services (1) O'Brien & Assoc
(1) City of Coppell TX (1) TechniStructures Reviewed by:
(1) City of Coppell TX ad, P.E.
(1) Rogers O'Brien Construction Co Senior Project Manager
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable
to the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical
materials.
CONCRETE COMPRESSIVE STRENGTH TEST
Report Number: 94051418.0220
Service Date: February 23, 2006
Client:
Transwestern Commercial Services
Attn: David Gunderson
5001 Spring Valley Rd Ste 600 W
Dallas TX 75244
'irefracon
8901 Carpenter Frwy, Ste #100
Dallas, Texas 75247
(214) 630-1010
Report Date: March 03, 2006
Project: AmberPoint Business Park
Buildings 4, 5 and 6
505 South Royal Lane
Coppell, TX
Project No.: 94051418
Material Information
Specified Strength: 3600 psi @ 28 Days
Batch Time: 8:06am Plant: On-site
Supplier: Potter Concrete
Truck No: 126 Ticket No: 103142
Mix I.D. No.: 7752
WaterAdded Onsite Before Test: 5Gallons
Water Added Onsite After Test: 0 Gallons
Field Test Data
Test Result
Slump, inches: 4.50
Air Content, %: 5.0
Concrete Temperature,o F: 61
Ambient Temperature,o F: 40
Plastic Unit Weight, pcf: 142.4
Laboratory Test Data
Set Specimen Diameter Area
No. ID (inches) (sq. inches)
1 1 6.00 28.27
1 2 6.00 28.27
1 3
1 4
Sample Information
Date Cast: February 23, 2006 Time: 8:36am
Technician: Barry Cuble
Weather Conditions: Overcast, cool, light winds
Accumulative Yards: 30/560
Placement Method: Pump
Sample Locations: 40' E & 25' N of S, see #1 of sketch
Placement Location: Pavement, see attached sketch
Specification Test Method
3-5 ASTM C143
3-6 ASTM C231
ASTM C1064
ASTM C1064
ASTM C138
Age at Maximum Compressive
Date Test Load Strength
Tested (days) (lbs) (psi)
03/02/2006 7 101,160 3,580
03/02/2006 7 102,580 3,630
Average (7 Days) 3,6'10
03/23/2006 28
03/23/2006 28
Services - Obtain samples of fresh concrete at the placement locations, perform required field tests and cast compressive
strength samples.
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT tesl methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable
to the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical
Page 1 of 4
CONCRETE COMPRESSIVE STRENGTH TEST
Report Number: 94051418.0220
Service Date: February 23, 2006
'lrerfacon
8901 Carpenter Frwy, Ste #100
Dallas, Texas 75247
(214) 630-1010
Client:
Transwestem Commercial Services
Attn: David Gunderson
5001 Spring Valley Rd Ste 600 W
Dallas TX 75244
Report Date: March 03, 2006
Project: AmberPoint Business Park
Buildings 4, 5 and 6
505 South Royal Lane
Coppell, TX
Project No.: 94051418
Material Information
Specified Strength: 3600 psi @ 28 Days
Batch Time: 9:14am Plant: On-site
Supplier: Potter Concrete
Truck No: 126 Ticket No: 103156
Mix I.D. No.: 7752
Field Test Data
Test
Result
Slump, inches: 5.00
Air Content, %: 4.8
Concrete Temperature,o F: 60
Ambient Temperature,o F: 42
Plastic Unit Weight, pcf: 143.2
Laboratory Test Data
Set Specimen Diameter Ama
No. ID (inches) (sq. inches)
2 1 6.00 28.27
2 2 6.00 28.27
2 3
2 4
Sample Information
Date Cast: February 23, 2006 Time: 9:29am
Technician: Barry Cuble
Weather Conditions: Ovemast, cool
Accumulative Yards: 170/560
Placement Method: Pump
Sample Locations: 85' E of W & 15' S of N, see #2 on sketch
Placement Location: Pavement, see attached sketch
Specification
3-5
3-6
Test Method
ASTM C143
ASTM C231
ASTM C1064
ASTM C1064
ASTM C138
Age at Maximum Compressive
Date Test Load Strenc, th
Tested (days) (lbs) (psi)
03/02/2006 7 106,390 3,760
03/02/2006 7 103,250 3,650
Average (7 Days) 3,710
03/23/2006 28
03/23/2006 28
Services - Obtain samples of fresh concrete at the placement locations, perform required field tests and cast compressive
strength samples.
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable
to the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical
materials.
CONCRETE COMPRESSIVE STRENGTH TEST
Report Number: 94051418.0220
Service Date: February 23, 2006
' reffacon
8901 Carpenter Fn,vy, Ste #100
Dallas, Texas 75247
(214) 630-1010
Client:
Transwestern Commercial Services
Attn: David Gundemon
5001 Spring Valley Rd Ste 600 W
Dallas TX 75244
Report Date: March 03, 2006
Project: AmberPoint Business Park
Buildings 4, 5 and 6
505 South Royal Lane
Coppell, TX
Project No.: 94051418
Material Information
Specified Strength: 3600 psi ~ 28 Days
Batch Time: 10:44am Plant: On-site
Supplier: Potter Concrete
Truck No: 120 Ticket No: 103172
Mix i.D. No.: 7752
WaterAdded Onsite Before Test: 10Gallons
Water Added Onsite After Test: 0 Gallons
Sample Information
Date Cast: February 23, 2006 Time: 11:11am
Technician: Barry Cuble
Weather Conditions: Cloudy, cool
Accumulative Yards: 330/560
Placement Method: Pump
Sample Locations: 170' E of W & 15' N of S, see #3 on sketch
Placement Location: Pavement, see attached sketch
Field Test Data
Test Result
Slump, inches: 5.25
Air Content, %: 5.0
Concrete Temperaturep F: 62
Ambient Temperature,o F: 46
Plastic Unit Weight, pcf: 142.4
Laboratorv Test Data
set specimen Diameter Area
No. ID (inches) (sq. inches)
3 1 6.00 28.27 03/02/2006
3 2 6.00 28.27 03/02/2006
3 3 03/23/2006
3 4 03/23/2006
Specification
3-5
3-6
Date
Tested
Test Method
ASTM C143
ASTM C231
ASTM C1064
ASTM C1064
ASTM C138
Age at Maximum Compressive
Test Load Strength
(days) (lbs) (psi)
7 103,320 3,650
7 97,560 3,450
Average (7 Days) 3,550
28
28
Services - Obtain samples of fresh concrete at the placement locations, perform required field tests and cast compressive
strength samples.
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable
to the actual samples tested at the location(s) referenced and are not necessarily indicative of the proper/ies of other appamntty similar or identical
materials.
CONCRETE COMPRESSIVE STRENGTH TEST
· Report Number: 94051418.0220
Service Date: February 23, 2006
' refracon
8901 Carpenter Frwy, Ste #100
Dallas, Texas 75247
(214) 630-1010
Client:
Transwestern Commercial Services
Attn: David Gunderson
5001 Spring Valley Rd Ste 600 W
Dallas TX 75244
Report Date: March 03, 2006
Project: AmberPoint Business Park
Buildings 4, 5 and 6
505 South Royal Lane
Coppell, TX
Project No.: 94051418
Material Information
Specified Strength: 3600 psi @ 28 Days
Batch Time: 12:08pm Plant: On-site
Supplier: Potter Concrete
Truck No: 126 Ticket No: 103187
Mix t.D. No.: 7752
WaterAdded Onsite Before Test: 15Gallons
Water Added Onsite After Test: 0 Gallons
Field Test Data
Test Result
Slump, inches: 4.50
Air Content, %: 5.2
Concrete Temperature,o F: 67
Ambient Temperature,o F: 52
Plastic Unit Weight, pcf: 142.4
Laboratory Test Data
set Specimen Diameter Area
No. ID (inches) (sq. inches)
4 1 6.00 28.27
4 2 6.00 28.27
4 3
4 4
Sample Information
Date Cast: February 23, 2006 Time: 12:27pm
Technician: Barry Cuble
Weather Conditions: Mostly cloudy, mild
Accumulative Yards: 480/560
Placement Method: Pump
Sample Locations: 80' W of E & 20' N of S, see ~4 on sketch
Placement Location: Pavement, see attached sketch
Specification
3-5
3-6
Test Method
ASTM C143
ASTM C231
ASTM C1064
ASTM C1064
ASTM C138
Age at Maximum Compressive
Date Test Load Strength
Tested (days.) (lbs) (psi)
03/02/2006 7 126,580 4,480
03/02/2006 7 127,410 4,510
Average (7 Days) 4,500
03/23/2006 28
03/23/2006 28
Services - Obtain samples of fresh concrete at the placement locations, perform required field tests and cast compressive
strength samples.
Technician: Barry Cuble
Report Distribution: ~
(1) Transwestern Commercial Services (1) O'Brien & Assoc
(1) City of Coppell TX (1) TechniStructures Reviewed by:
(1) City of Coppell TX Hussein H. Abusaad, P.E.
(I) Rogers O'Brien Construction Co Senior Project Manager
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable
to the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical
materials.
CONCRETE PLACEMENT OBSERVATION SKETCH
'l ffacon
Date of Service:
Client No.:
Client:
02/23/06
50854
Transwestem Commercial Services
5001 Spring Valley Rd Ste 600 W
Dallas, TX 75244
Report No.:
Project No.:
Project:
94051418.0220
94051418
AmberPoint Business Park
Buildings 4, 5 and 6
505 South Royal Lane
Coppell, TX
Not to Scale
t
N
Building #4
Existing Pavement
- 310'
Placed 2/23/06
Existing Pavement
CONCRETE COMPRESSIVE STRENGTH TEST
Report Number: 94051418.0149
Service Date: February 2, 2006
'lrerracon
8901 Carpenter Frwy, Ste #100
Dallas, Texas 75247
(214) 630-1010
Client:
Transwestem Commercial Services
Attn: David Gunderson
5001 Spring Valley Rd Ste 600 W
Dallas TX 75244
Report Date: March 03, 2006
Project: AmberPoint Business Park
Buildings 4, 5 and 6
505 South Royal Lane
Coppell, TX
Project No.: 94051418
Material Information
Specified Strength: 3600 ps[ ~ 28 Days
Batch Time: 5:01am Plant: 2
Supplier: Potter Concrete
Truck No: 113 Ticket No: 102507
Mix I.D. No.: 7752
Water Added Onsite Before Test: 0Gallons
Water Added Onsite After Test: 10 Gallons
Sample Information
Date Cast: February 2, 2006 Time: 5:16am
Technician: Marlo A. Garcia
Weather Conditions: Cool w/mild breeze
Accumulative Yards: 30/130
Placement Method: Direct Discharge
Sample Locations: See attached sketch for Location #1
Placement Location: Pavement, See attached sketch for area
poured
Field Test Data
Test
Specification
Result
Slump, inches: 5.50
Air Content, %: 5.7
Concrete Temperature,o F: 68
Ambient Temperature,o F: 57
Plastic Unit Weight, pcf:
Laboratory Test Data
set Specimen Diameter Area
No. ID (inches) (sq. inches)
1 1 6.00 28.27 02/09/2006
1 2 6.00 28.27 02/09/2006
1 3 6.00 28.27 03/02/2006
1 4 6.00 28.27 03/02/2006
3-5
3-6
Date
Tested
Test Method
ASTM C143
ASTM C231
ASTM C1064
ASTM C1064
ASTM C138
Age at Maximum Compressive
Test Load Stren~.th
(days) (lbs) (ps~)
7 84,290 2,980
7 94,240 3,330
Average (7 Days) 3,160
28 128,330 4,540
28 134,600 4,760
Average (28 Days) 4,650
Comments: Not tested for plastic unit weight.
Services - Obtain samples of fresh concrete at the placement locations, perform required field tests and cast compressive
strength samples.
The tests were performed in general accordance with applicable ASTM, AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company, Test results transmitted herein are only applicable
to the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical
materials.
CONCRETE COMPRESSIVE STRENGTH TEST
· Report Number: 94051418.0149
Service Date: February 2, 2006
']refracon
8901 Carpenter Fn,vy, Ste #100
Dallas, Texas 75247
(214) 630-1010
Client:
Transwestem Commercial Services
Attn: David Gunderson
5001 Spring Valley Rd Ste 600 W
Dallas TX 75244
Report Date: March 03, 2006
Project: AmberPoint Business Park
Buildings 4, 5 and 6
505 South Royal Lane
Coppell, TX
Project No.: 94051418
Material Information
Specified Strength: 3600 psi ~ 28 Days
Batch Time: 6:03am Plant: 2
Supplier: Potter Concrete
Truck No: 122 Ticket No: 102517
Mix I.D. No.: 7752
WaterAdded Onsite Before Test: 0Gallons
Water Added Onsite After Test: 5 Gallons
Sample Information
Date Cast: February 2, 2006 Time: 6:18am
Technician: Marlo A. Garcia
Weather Conditions: Cool w/mild breeze
Accumulative Yards: 130/130
Placement Method: Direct Discharge
Sample Locations: See attached sketch for Locaton #2
Placement Location: Pavement, See attached sketch for area
poured
Field Test Data
Test
Result
Slump, inches: 5.50
Air Content, %: 5.5
Concrete Temperaturep F: 67
Ambient Tempereture,o F: 57
Plastic Unit Weight, pcf:
Laboratory Test Data
Set Specimen Diameter Area
No. ID (inches) (sq. inches)
2 1 6.00 28.27
2 2 6.00 28.27
2 3 6.00 28.27
2 4 6.00 28,27
Specification
Test Method
3-5 ASTM C143
3-6 ASTM C231
ASTM C1064
ASTM C1064
ASTM C138
Age at Maximum Compressive
Date Test Load Strength
Tested (days) (lbs) (psi)
02/09/2006 7 112,770 3,990
02/09/2006 7 108,960 3,850
Average (7 Days) 3,920
03/02/2006 28 146,140 5,170
03/02/2006 28 145,100 5,130
Average (28 Days) 5,t$0
Comments: Not tested for plastic unit weight·
Services - Obtain samples of fresh concrete at the placement locations, pedorm required field tests and cast compressive
strength samples.
Technician: Marlo A. Garcia
Report Distribution: ~
(1) Transwestern Commercial Services (1) O'Brien & Assoc
(1) City of Coppell TX (1) TechniStructures Reviewed by: .
(1) city of coppe[I TX Hussein H. Abusaad, P.E.
(1) Rogers O'Brien Construction Co Senior Project Manager
The tests were performed in general accordance with applicable ASTM. AASHTO, or DOT test methods. This report is exclusively for the use of the client
indicated above and shall not be reproduced except in full without the written consent of our company. Test results transmitted herein are only applicable
to the actual samples tested at the location(s) referenced and are not necessarily indicative of the properties of other apparently similar or identical
materials.