ST 99-02 A, West Sandy Lake Rd - Work Activity Update
Week of 3/6 to 3/10
1. The proposed change in grade and elevation of the 33" RCP from approximate STA 5+98
through STA 8+99 was received from Teague, Nail & Perkins and forwarded to Tiseo to
alleviate the conflict with TXU's underground duct bank.
2. Contractor installed the fire hydrant at approximate STA 24+39.
3. Contractor began lowering the existing 12" water main at approximate STA 18+00 and
approximate STA 15+60.
4. Contractor relocated and tested the fire hydrant at approximate STA 49+40.
5. Contractor cut and plugged the existing 10" water main at approximate STA 52+40.