ST9902-CS060308March 8, 2006 John Gay, Project Manager Tiseo Paving Company, Inc. 419 E. H~3' 80 Mesquite, TX 75105 RE: West Sandy Lake Road Project # ST 99-02A Storm Drain Line C Conflict Dear Mr. Gay: You are probably aware now' of the conflict between the Line C slorm drain at St 6+80 and the TXU underground duct bank. This conflict will require the re-laying of approximately 115' of Line C. TXU was contacted for a proposal to relocate their underground facility but the cost to peribrm the work was prohibitive, and the time frame would have delayed work on your contract with us. Attached are two copies of revisions to the profile for the storm drain line. Please provide the City a proposal for the extra work to modify the profile of storm drain Line C. If you have any questions or need any additional information please feel free to contact me. Sincerely, Keith R Marvin, P.E. Assistant City Engineer Office 972/304-7044 Fax 972/304-3570 CC: Suzan Taylor, CIP Coordinator Larry Davis, Construction Inspector Matt Atkins, P.E., Teague Nail & Perkins