Vista Point 2R-CS060223DEVELOPMENT REVIEW COMMITTEE
ENGINEERING COMMENTS
ITEM:
Vista Point lit Lot 2, Block At Replat, to revise thc locations of the fire lanes to
allow the development of three buildings containing a total of approximately
115,525-square feet on 10.046 acres of property located along the west side of
MacArthur Boulevard., south of S.H. 121, at the request of Christopher
Gardner, Jackson Shaw.
STAFF REP.: Marcie Diamond PROJECT ID# RP-06-0010
DRC DATE: March 2, 2006
CONTACT:
COMMENT STATUS:
,,"PRELIMINARY
972/304-3686
Plat
1. The ROW along SH 121 that was dedicated for a right-hand turn lane will no longer be
required. Do you want it back???
Grading and Drainage Plan
1. Additional information will be needed in order to perform a review of the grading and
drainage plan. Include drainage areas and calculations on this sheet.
Water and Sanitary Sewer Plan
1. Fire hydrants are required every 300' along the fire lane. You will need additional
hydrants.
2. FDC's should be located 1.5 times the building height away from the building, on the
same side of the fire lane as and within 50' of a fire hydrant..
3. Install a main line isolation valve at least every 500' along the fire line.
4. Ensure that the most recent version of the existing off-site infrastructure is shown on
these plans.
5. The plans call for 2 ½" domestic meters however, the City's largest domestic water
meter is 2".
6. Manholes should be provided where the 6" sanitary sewer laterals tie to the 8" sanitary
sewer mains.
7. Verify the existence of the sewer stub shown from Lot 6.
8. Supply a utility plan showing the entire water system for the development.
Additional comments may be generated upon detailed engineering review.
DEVELOPMENT REVIEW COMMITTEE
ENGINEERING COMMENTS
ITEM:
PD-199R3-HC~ Vista Point II, Lot 2~ Block A, zoning change request from PD-
199-HC (Planned Development-199-Highway Commercial) to PD-199R3-HC
(Planned Development-199 Revision 3-Highway Commercial) to attach a
Detail Site Plan to allow the development of three buildings containing a total
of approximately 115,525- square feet on 10.046 acres of property located
along the west side of MacArthur Boulevard, south of S.H. 121, at the request
of Christopher Gardner, Jackson Shaw.
STAFF REP.: Marcie Diamond PROJECT ID# PD-06-0009
DRC DA TE: March 2, 2006
Site Plan
1. The monument sign that is proposed inside the 15' Utility Easement along Forest Hill
Drive should be located outside the easement.
2. The site plan does not match the utility plan. They should be consistent.