Wagon Wheel Park Outfall StructureCS060302 (2)COPPELL
MEMORANDUM
TO: Brad Reid, Director of Parks and Recreation Department
FROM:I.~-~ Keith Marvin, P.E., Asst. City Engineer
DATE: March 2, 2006
REF:
Bid/Contract #Q-0206-01
Wagon Wheel Park Outfall Structure
Drainage Project #DR 05-01
On February 14, 2006 the City of Coppell received and opened seven bids for the construction of
the Wagon Wheel Park Outfall Structure.
The bids on this project ranged from a low bid of $109,443.00 to a high bid of $289,400.00. The
low bidder was Vortex Construction, Inc. in an amount of $109,443.00, with an estimated
completion time of 60 calendar days There was an error in completion of the bid form by
Vortex, however, the Purchasing Agent has determined that Vortex Construction's bid is valid
(see attached memo).
This contractor has not performed any work for the City of CoppelI in the past, however they
were able to supply references from area projects. In speaking with the references provided, I
received no negative feedback that would indicate that they are not able to complete the project
on time, and within budget.
The Engineering Department completed the design of this project in house, and our estimate was
$99,300. If you have any questions please give me a call at 972/304-3679.