SS9901-CN060510CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT Deforest Rd & Sandy Lake Rd. Lift Station Improvements SS 99 -01 CONTRACTOR Can -Fer Construction Company OWNER. City of Coppell CHANGE ORDER NO Five (5) DATE May 8, 2006 Item Description Quantity Unit Unit Price Total Add: New Furnish & Install Two - 22 5 deg. I LS 2,00457 2,00457 MJ D I. Bends w /accessories Total Revision to Contract Amount / Change Order #5 $2,004.57 Original contract amount $2,621,361.84 Net increase in contract amount Change Order # 1 - I2, Net increase in contract amount Change Order # 2 - 8,'24'05 Net increase in contract amount Change Order # 3 - i io;o(, Net increase in contract amount Change Order # 4 - 2.22 /06 Net increase in contract amount Change Order # 5 - 5,'8,06 Revised contract amount Net increase in contract time of completion Revised contract li of completion $1,13000 518,721 30 $7,495 39 $7,390 15 $2,004.57 $2,623,366.41 1 Days 315 C alendar Days The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. r } f�i •; Recommended b� City Engineer Date Accepted by City Date 1 Agreed to by Contractor Date