Vista Point 2R-CS060512
THE
C I T Y
o F
COPPELL
~.- ' '. ... l /.<, )?' ,-"';;
.\C "'=.- ~<.;'!."-,,, .'. /~ ,yo/'::.l"',~ -"'.
\ ~~-~~ ^ "".<y:;;:,,? \
/' -~-~. ""-">.-~ \J
( -... ~. > __ ~""""J q
-\' "'. II
'\ ,) \
May 12, 2006
Enk HauglIe, P E
Pacheco Koch Consultmg Engmeers
8350 N Central Expressway, SUite 1000
Dallas, TX 75206
RE: Vista Pomt II, Lot 2R, Block A
Fee Assessment Letter
Dear Mr Haughe
Enclosed IS a copy of the Cn) of Coppell Development Fee Assessment table, along with a copy of the
Development Fee calculatIOns for the referenced development.
Please make payment for th~ Impact Fees to the elt;; of Coppell m the amount of $55,971 86 and forward
to the Engmeenng Department along with a COP) of the Fee Assessment table ThiS amount IS a portIOn of
the assessed fees that need to be paId pnor to fihng of the final plat Please note that the Texas
LegIslature, under Senate BIll 243, delayed the collectlon of Water and Sewer Impact Fees untIl the
Issuance of a BUIldmg Permit. Please provide a I;OPY of the EngIneer's estImate or contract to our office
so the 2% & 4% constructIOn mspectIOn fee can be venfied The constructIon mspectIOn fees must be
paId pnor to the scheduled pre-constructIOn meetIng
The additIOnal fees for \\cater and sewer taps water meters, and utJl1t\ mspectlOn fees need to be paid by
,>eparate check at the new Publtc W nrks Service Center, 8 J 6 S Coppel! Road. Meters wIll be ordered
when those fees are pa:d
Appropnate paYl1lent of the reqUIred fees will help Insure a succes3fu] hegll1l11ng of thiS proJect We look
forward to workIng with you on thIS project. If you have an) quesllons, plea~e contact me
SIncerely,
~~~
Charlene La MattIna. E I T
Graduate EngIneer
cc Jenmfer Armstrong, FInance Director
Mary Beth Spletzer. AdmInistratIve Secretary, B1llldIng InspectIOns
Glenn Hollowell, ,\SSlstant Director of PublIc Works
Greg Jones, ChIef BUlldmg OffiCial
Brad Reid, Director of Parks and Recn:atwn
L 5 5 PAR r: W A * PO R:J X q 4 ., f * r Ll r= F ELL T,., 7 '5 0 l!.J * TEl:.:l 7 4 I (l 0 2 L * r A)i. ~ 7 2. / ~ n 4 "J 6 'I 3
DEVELOPMENT FEE TABLE
Project: Vista Point II, Lot 2R, Block A
Date: 5/10/2006
TOTAL AMOUNT DUE
FEES DUE PRIOR TO
FILING
PLAT
Water Impact Fee $23,985 00
(100% due at Issuance ofBUIldmg Permit)
Water Tap InspectIon Fee $250 00
(100% due at Issuance of Water Meter)
Water Meter Fee (DomestIc) $613 02
(100% due at Issuance of Water Meter)
Water Meter Fee (IrngatIOn/FlrelIne) $408 68
(100% due at Issuance of Water Meter)
Water Meter Deposit (DomestIc) $9000
(100% due at Issuance of Water Meter)
IrngatIOn/Flrehne Meter Deposit $6000
(100% due at Issuance of Water Meter)
Wastewater Impact Fee $14,391 00
(100% due at Issuance ofBUIldmg Permit)
Wastewater Tap InspectIOn Fee $15000
(100% due at Issuance ofBUIldmg PermIt)
UtIlIty Fmal InspectIon Fee $15000
(100% due at Issuance of BUIldmg PermIt)
Park Fee $000 $000
(100% due pnor to FIlmg Plat)
Roadway Impact Fee $55,971 86 $55,971 86
(100% due pnor to FIlmg Plat)
Street Light Fee InformatIon not A vmlable
(100% due pnor to Acceptance of Project) II
Street SIgn Fee Informatlon not A vallable
(100% due pnor to Acceptance of ProJect) II
ConstructIOn InspectIOn Fee InformatIon not Available
(100% due pnor to Start of ConstructIOn) I
ITOT AL II $96,069 561
TOT AL AMOUNT DUE PRIOR TO FILING FINAL PLAT $55,971 86
DEVELOPMENT FEE WORKSHEET
PROJECT:
DATE:
Vista Point II, Lot 2R, Block A
5/10/2006
Water Impact Fee:
Domestic Meter(s) 3 - 2 inch = 1599 ESU's
Irrigation Meter(s) 2 - 2 inch = 1066 ESU's
0 = 0 ESU's
Fireline Meter(s) 0 = 0 ESU's
Total #- 2665 ESU's @ $900 00 ea
(Due prior to issuance of building permit)
$23,98500
Water Tap Inspection Fee:
Total #'
5 Connections @ $50 00 ea_
(Single family due prior to issuance of building permit)
(All other developments due prior to issuance of meter)
$250 00
Domestic Water Meter Fee:
Total #- 3 Domestic Meter(s) @ $20434
(Single family due prior to issuance of building permit)
(All other developments due prior to issuance of meter)
$613 02
Irrigation/Fireline Water Meter Fee:
Total #- 2 Irrigation Meter(s) @
Total #. 0 Additional Irrigation Meter(s) @
Total #. 0 Fireline Meter(s) @
(100% due prior to issuance of water meters)
$204 34
$000
$000
$408 68
$000
$000
Domestic Water Meter Deposit Fee:
Total #' 3 Meter(s) @ $30 00 ea.
(100% due prior to issuance of water meters)
$9000
Irrigation/Fire Meter Deposit Fee:
Total #- 2 Meter(s) @ $30 00 ea.
(100% due prior to issuance of water meters)
$60 00
Wastewater Impact Fee:
Total Domestic Meters ESU's 1599 @ $900 00 ea
(Due prior to issuance of building permit)
$14,391 00
Wastewater Tap Inspection Fee:
Total #. 3 Connections @ $50 00 ea,
(100% due prior to issuance of building permit)
$15000
Utility Final Inspection Fee (All developments):
Total #. 3 Lots @ $50 00 ea
(100% due prior to issuance of building permit)
$15000
Park Fee (For Residential Developments Only):
Page 1
DEVELOPMENT FEE WORKSHEET
* Preliminary plat approved:
After October 26,1993
o
o
Single-family @ $0 00 per lot
Multi-family @ $0 00 per unit
(100% paid prior to Council approval of final plat)
Roadway Impact Fee:
(See attached fee calculations)
Street Lighting Fees:
Assessed for lighting in the City's right-of-way
This fee cannot be assessed until after T U Electric submits
the lighting plan for the proposed development.
Once the plans are submitted, $292.60 per light will be assessed
(100% due prior to final acceptance of development)
Street Sign Fees:
Assessed for signage in the City's right-of-way
(See attached fee calculations if applicable)
Construction Inspection Fees:
A copy of the development contract must be submitted for assessment.
The contracts should indicate the cost to construct the improvements
that are inspected by the Engineering Department.
(2% of development cost required for private improvements)
(4% of development cost required for public improvements)
Page 2
$000
$000
$55,971 86
Information not Available
Information not Available
Information not Available
ROADWAY IMPACT FEE CALCULATIONS
PROJECT:
DATE:
Vista Point Il, Lot 2R, Block A
5/10/2006
ROADWAY IMPACT FEE:
1
Li ht Industrial
General Li ht Industrial
115,525
115.53
3.23
$150
$55,971.86
* (Figure 4 1 - Roadway Impact Fee Study)
** (Table 4 10- Roadway Impact Fee Study)
*** (Schedule 2, Page 3 - The Master Fee Schedule)
A.MOJJJ\{TDU$,. . .
'$55.97i,g~ .~