Loading...
ST0004(2006)-CS060601T H E C 1 T Y O F COFFELL June 1, 2006 Sam L. Garrett Advanced Paving Company 2257 Joe Field Road Dallas, TX 75229 RE Freeport Parkway Reconstruction Project # ST 00-04'2006' Dear Mr Garrett: This letter is written to reiterate concerns about progress on the referenced prclect. It appears that the project will not be completed within the allotted contract time Advanced Paving requested and was granted an extension of 21 days to the contract time That time will be up on June 10, 2006, and according to the most recent pay request approximately 50° O of the work must still be completed. We have been flexible to date concerning contract time as long as your crews had been diligently working towards completion. Since we accommodated your request for additional time, we feel that you should be trying to meet that revised completion time The city inspector feels that the current daily activity does not reflect an effort to meet that time This contract does have a provision for liquidated damages that will be enforced if a significant effort is not made to meet this contract time If you have any questions about the subjects of this letter, please contact me at your convenience Sincerely, Keith R. Marvin, P.E Assistant City Engineer Office 972/304 -7044 Fax 972/304 -3570 cc Rick O'Dell, Construction Inspector P 11 BOX 147H * — F FELL T T L L 9 -2 11 n022 * FAX y72 304 3673