Big Cedar-CS 900201 COST ANALYSIS Bethel School Road Expansion COPPELL, TEXAS FEBRUARY, 1990 ' BETHEL SCHOOL ROAD EXPANSION QUANT. UNIT DESCRIPTION UNIT $ TOTAL 1,000 CY Street Excavation 1.50 $ 1,500.00 0.5 AC Clear and Grub 4,000.00 2,000.00 TOTAL- EARTHWORK $ 3,500.00 ,~IITARY SEWER QUANT. UNIT DESCRIPTION UNIT $ TOTAL 360 LF 8" SDR 35 18.00 $ 6,480.00 I EA 4'-0 Standard Manhole 1,600.00 1,600.00 I EA Tap Existing Manhole 1,000.00 1,000.00 I I.~ Sanitary Sewer Test 1,500.00 1,500.00 360 LF Vicleo Camera Inapectlon 2.00 720.00 TOTAL -- SANITARY SEWER $ 11,300.00 OUANT. UNIT DESCRIPTION UNIT $ TOTAL 60 LF 21' RCP 35.00 $ 2,100.00 2 EA 21' Type "B" Headwall 750.00 1,500.00 1,200 LF Grade to Drain 2.00 2,400.00 TOTAL-- 81'ORM SEWER $ e,O00.00 QUANT. UNIT DESCRIPTION UNIT $ TOTAL 950 LF 8" DR 14 18.00 $ 17,100.00 50 LF 6" DR 14 16.00 800.00 I EA 6" Gate Valves 400.00 400.00 I EA Fire Hydrants 1,200.00 1,200.00 2 EA 8" Gate Valves 500.00 1,000.00 1 TN Cast Iron Fittings 2,000.00 2,000.00 1 EA 8' Plug 100.00 100.00 3 EA Connect to Exlating Water 500.00 1,500.00 1 LS Test Water System 1,000.00 1,000.00 TOTAL-- WATER $ 26,100.00 ELECTRIC AND GAS QUANT. UNIT DESCRIPTION UNIT $ TOTAL 3 EA Relocate Power Pole~ 1,000.00 $ 3,000.00 _ TOTAL -- ELECTRIC AND GAS $ 3,000.00 T~ENCH SAFETY QUANT. UNIT DESCRIPTION UNIT $ TOTAL I LS Trench Safety Design 1,000.00 $ 1,000.00 350 LF Trench Safety Program 0.50 175.00 TOTAL - TRENCH SAFETY $ 1,175.00 QUANT. UNIT DESCRIPTION UNIT $ TOTAL 1 ~477 ~ Asphalt Pulverl-___~on 2.15 $ 3,175.55 2O0 GAL RC 25O 7.00 1.400.00 TOTAL- PAVING $ 57~'.25.55 TRAFFIC CONTROL QUANT. UNIT DESCRIPTION UNIT $ TOTAL 250 EA P15Y Button 4.50 $ 1,1 25.00 2 EA Stirnsonite Button 15.00 30.00 2 EA WI~tR Signs 250.00 5(X).00 1 EA W14~R Sign 250.00 250.00 1 EA W2~t Sign 250.00 250.00 1 EA W1-6 Sign 250.00 250.00 I EA W5-1 Sign 250.00 250.00 3 EA W-8 Sign 175.00 525.00 TOTAL -- TRAFFIC CONTROL $ 3,180.00 QUANT. UNIT DESCRIPTION UNIT $ TOTAL I LS Subgrade and Paving 750.00 $ 750.00 I LS Densiti~ 1,000.00 1,000.00 TOTAL -- TESTING $ 1,750.00 SUMMARY EARTHWORK $ 3,500.00 SANITARY SEWER $ 11,300.00 STORM SEWER $ 6,000.00 WATER $ 25,100.00 ELECTRIC AND GAS $ 3,000.00 TRENCH SAFETY $ 1,175.00 PAVING $ 57,225.55 TRAFFIC CONTROl. $ 3,180.00 TESTING ~ SUBTOTAL $ 112,230.55 CONTINGENCY (10~ OF 112,230.55) ~ . SUBTOTAL -- CONSTRUCTION $ 123,453.60 Engineering Costs (12~ o~ $123,453.60) $ 14,814.43 GRAND TOTAL $ 138,268.03 NOI~4 ~ ~9.0.% .076