Amberpoint BP 2R-LR060526REPORT OF REINFORCING STEEL OBSERVATION lt~rracon
Consultlnp Engineers 3 SWentlsts
8901 Carpenter Frwy Suite #100
Dallas, 'texas 75247
f2141ti30-1010
Date of Service
Client No.•
Client:
Services.
05/26/06
50854
Report No : 94051418 0417
Project No.• 94051418
Transwestern Commercial Services Project: AmberPomt Business Park
5001 Sprang Valley Rd Ste 600 W Buildings 4, 5 and 6
Dallas, TX 75244 505 South Royal Lane
Coppell, TX
Observe placement of reinforcing for compliance with furnished drawings
PROJECT DATA
Drawings Utilized
CO O1 and C1 O1, dated 04/10/06
Locations/Items Observed: Pavement, Parking and Fire Lanes, Nearest to Bulding on E Side of Building #4
Pavement, from SE corner of Building #4 to NE corner of Building #4
Test Method Visual Observation
REPORT OF OBSERVATION
ITEMS OBSERVED CORRECT INCORREC7 ITEMS OBSERVEb CORRECT INCORRECT ITEMS OBSERVED CORRECT INCORRECT
Placing Drawings Approved X Bar Length and Shape X Column Tie Spacing & Type
Bar Size X Proper Bar Placement X Stirrup Spacing & Type
Bar Grade X Properly Tied X Welded Splices
Rebar Clean X Dowel Bars in Place X Mechanical Splices
Trash 8 Debris Removed X Proper Bar Supports ~{ Lapped Splices X
Number of Bars X Proper Cover/Clearance X
Discrepancies/Comments The following discrepancies were noted and corrected at the rime of this observation.
1 Dowels were bent downward from truck traffic Dowels were raised and
straightened out before placement of concrete
Field Results Report To Jeff Slama
Technician: E Jerigan
Report Distrilaution:
(1) Transwestern Commercial Services
(1) City of Coppell TX
(1) City of Coppell TX
(1) Rogers O'Brien Construction Co
(1) O'Brien & Assoc
(1) TechniStructures
Hussein H. Abusaad, P.E.
Senior Project Manager
309acs This report is exGusively for the use of the client indicated above and shall not be reproduced without written approval of Terracon.