ST9902-CS060615Suzan Taylor - RE. FW W S Lake From: "Carl Lee" <clee @cmjengr com> To: "'Suzan Taylor "' <staylor @ci.coppell.tx.us> Date: 6/15/2006 8 39 AM Subject: RE. FW W Sandy Lake Susan, thank's for the information! As far as our Bill code goes, the 1001 code would represent the labor charges associated with concrete testing We are working through our "work remaining" testing cost estimate At this time it looks like we are still on budget overall I will be sending you the estimate in a few days R. Carl Lee - -- - - - -- Original Message---- - From Suzan Taylor [mailto staylor @ci.coppell.tx.us] Sent: Wednesday, June 14, 2006 10 41 AM To Amanda Walker; clee @cmjengr com Subject: Re FW W Sandy Lake Carl: The inspector asked me to forward this information to you to use in the comparison The following densities are completed: 1 The roadway fill on the eastbound lanes 2. Under the N Coppell Road pavement 3 The storm drain trenches 4 Box culvert trenches 5 Lateral trenches under the eastbound portion We still need densities on the following - 1 Storm drain trenches at Oakbend and Branchwood and the lateral crossings under the westbound lanes 2 Densities for the fill outside the pavement on N Coppell Road. 3 The trench for the 48 -inch storm drain that will be removed and backfilled 4 The subgrade fill on the westbound lanes 5 Finished subgrade on east and westbound lanes at 300 feet 6 Two retaining wall at Oakbend and Branchwood What services are included in Bill Code 1001 concrete Inspection? Let me know if you have any questions for me or Larry concerning this. Suzan Taylor >>> "Amanda Walker" <awalker @cmjengr com> 6/12/2006 11 35 AM >>> Ms. Taylor - We will compare what has been done verses what is left to do in regards to the construction and our testing budget. Please find attached an updated budget for the project. Sincerely, P age 1 F 1 �� Suzan Taylor -RE FW W Sandy Lake R. Carl Lee - - - -- Original Message---- - From Carl Lee [mailto clee @cmjengr com] Sent: Monday, June 12, 2006 1054 AM To awalker @cmjengr com Subject: FW W Sandy Lake - - - -- Original Message---- - From Suzan Taylor [mailto staylor @ci coppell.tx.us] Sent: Friday, June 09, 2006 8.21 AM To clee @cmjengr com Subject: W Sandy Lake Carl: The projected budget for the project calls for 281 in -place moisture density tests and the last budget report shows that there are 169 units remaining Larry Davis, inspector for the project, does not think there are sufficient density tests left in the budget to complete the project. Would you please compare the remaining number of density tests with the amount of work remaining and see how many more tests you think we will need to complete the project. We want to increase the budget before the end of the project and will have to take the revised budget to the city council for approval Also, Larry wants to make sure that all re -test and cancellations are being charged to Tiseo Your consideration of this matter is appreciated Page :� Suzan Taylor 972 - 304 -7019