Denton Tap 3A-CS060630To:
From:
Date: June 30, 2006
T H E •C 1 T Y •O F
COPPELL
MEMORANDUM
FROM THE
DEPARTMENT OF ENGINEERING
Ken Griffin, Director of Engineering
Glenn Hollowell, Asst. Director of Public Works
Greg Jones, Chief Building Official
Tim Oates, Fire Marshal
Larry Davis, Construction Inspector
Office Phone: (972) 304 -3684
Fax: (972) 304 -3570
RE: WALK -THRU INSPECTION for Denton Tap Development, Lot 3 Block A
(Coppell Montessori Academy)
A final walk -thru for paving, utilities and drainage on the referenced project has been
scheduled for:
Thursday, July 6th at 9:00 a.m.
Please let me know if I can be of further assistance.
cc: Ken Head, Head Construction fax 214/722 -7635
"CITY OF COPPELL ENGINEERING EXCELLENCE BY DESIGN"