Loading...
DR9801-CS 990219 Weekly Progress Report Offsite Drainage and Paving Improvements Progress Report No. 7 Date: February 19, 1999 Time: 3:00 PM Temp: 70's Weather: sunny Contr. Wright Construction Equip.: dump track, front-end loader Halff Associates arrived on site at approximately 3:00 pm on February 19 for construction observation. At the 60" RCP site at Fritz Drive and Freeport Parkway, the riprap has been installed at the headwall. Grassing still needs to be done at this location. At the 8'x 5' box culvert site, Sutton still needs to seal the joints in the pavement. Wright has placed riprap around both headwalls; however, cleanup and grading still need to be done around the east headwall to provide positive drainage through the system. A front-end loader was loading the spoil materials into a dump truck to be removed from the site. At the 54" RCP and drive site at the intersection of Freeport Parkway and 1-635, all of the pavement has been poured and the brick pavers have been installed. The joints still need to be sealed. The median needs to be backfilled. Erosion control measures need to be provided at the "y" inlet at the northeast coruer of Freeport Parkway and 1-635. A hole was left in the pavement for the 2' x3' traffic rated concrete box to be installed. Another concrete box was found to the south of the pavement. I could not tell whether this box is to be installed at that location or this is the old box that was removed. inACC°rdingplace alongt° TimFreeportMUllikin,parkway.the 3" PVC conduit has been installed. Traffic barrels were It has been a pleasure working with you on this project. If you have any comments or questions, please contact me by phone at (214) 346-6246 or by fax at (214) 361-5573. Todd Jackson HALFF ASSOCIATES, INC. cc: Robert McCann, Catellus Development Corporation Tim Mullikin, Wright Construction